Explainer · Power
Sources for the gigawatt campus figures
The numbers behind the November 24, 2026 post on AI/SI campuses, with a dated source for each line.
November 24, 2026 · Figures are as published by each source on the date shown
Running figures are Epoch AI estimates as of November 23, 2026, shown in gigawatts. Planned figures come from company announcements and Epoch AI, as dated below. When those sources disagree, this page says so and uses the most authoritative dated figure.
Running now
Amazon Rainier, 1.0 GW, Indiana
Epoch AI estimate of 1,037 MW of IT power, last updated November 23, 2026. The post shows this as 1.0 GW.
SpaceXSI Colossus 2, 0.9 GW, Tennessee
Epoch AI estimate of 946 MW, November 23, 2026. The post shows this as 0.9 GW.
OpenAI Abilene, 0.8 GW, Texas
Epoch AI, November 23, 2026. The post shows this as 0.8 GW.
Being built, completion targets
- Hyperion: around 2032
- Cheyenne: 2031
- Fairwater: 2028
- Colossus 2: no public date
- OpenAI/Oracle New Mexico: 2028
- Prometheus: no public date
Sources for each date are in the campus notes below. If a company has not published a completion date for the figure in the chart, the line says "no public date."
Under construction in the United States
Figures are planned unless noted.
Microsoft Fairwater, 2.3 GW, Wisconsin
Epoch AI estimate of 2,263 MW of IT by 2028, last updated November 23, 2026. Microsoft has not published a megawatt figure. The first Mount Pleasant building is already operating (Microsoft, June 23, 2026).
Meta Hyperion, 5.0 GW, Louisiana
Meta official, July 13, 2026, "5 GW in compute capacity," Richland Parish, Louisiana. A Meta spokesperson told CNBC the same day that the full 5 GW project should be complete around 2032, and that the site should reach 2 GW by 2030. Those are different milestones than first traffic: in a November 23, 2026 interview, Meta vice president Rachel Peterson said the company anticipates serving traffic by the end of 2027. Epoch projects about 1,632 MW of IT by 2028, a smaller near-term figure.
Google Cheyenne, 2.7 GW, Wyoming
Laramie County planning coverage (Cowboy State Daily, July 8, 2026). Google's official November 5, 2026 post announced a $17 billion first Wyoming campus but did not state a campus megawatt total or a completion date. It did mention a 702 MW fuel-cell power contract. Local reporting and Data Center Dynamics say the full campus is slated to be completed in 2031, with a portion expected to begin operations in the second half of 2028.
Google, November 5, 2026 · Cap City News, September 10, 2026 · Data Center Dynamics, November 6, 2026
OpenAI / Oracle, 1.8 GW, New Mexico
Epoch estimate of 1,750 MW of IT, due in the fourth quarter of 2028. Some reports cite up to 2.45 GW of on-site fuel-cell power, a different measure. Doña Ana County's project page says the initial 400-acre phase, including the microgrid, is expected by the third quarter of 2028.
Epoch AI · Epoch AI, Stargate New Mexico · Doña Ana County project commitments
Meta Prometheus, 1+ GW, Ohio
Meta says the New Albany, Ohio cluster will deliver over 1 GW. The first phase is already complete (Meta Engineering, October 19, 2026). Meta has not published a date for reaching the full 1+ GW figure.
SpaceXSI Colossus 2, 2.0 GW, Tennessee
Planned cluster scale per Musk and DCD (November 2, 2026). The running figure of 0.9 GW is Epoch's 946 MW, November 23. Gun Range and Spam halls were tracking online by the end of November and December (Elon Musk, October 31). SpaceXSI has not published a completion date for the 2.0 GW campus scale.
Anthropic / Fluidstack, Texas and New York
Anthropic and Fluidstack announced a $50 billion build, "gigawatts of power," with sites due through 2026. No campus megawatt figure was published.
OpenAI Michigan, Wisconsin and Texas, 1+ GW each
OpenAI's Michigan campus is "more than one gigawatt" (October 30, 2025). Wisconsin (Port Washington) and Texas (Shackelford, Milam) are also planned at about a gigawatt or more. Lordstown, Ohio is not.
SpaceXSI Southaven plant, 1.2 GW
Company fact sheet and a Mississippi PSD permit dated March 11, 2026. Forty-one turbines are widely reported. The permit was upheld November 10, 2026.
Rainier "more than 2.2 GW" for the full New Carlisle site comes from CNBC, October 29, 2025, citing Amazon. Epoch's planned IT figure for that campus is 1,925 MW by 2028. The running line uses Epoch's 1,037 MW, shown as 1.0 GW.
International, planned or building
OpenAI Abu Dhabi, 1.0 GW, UAE
Official Stargate UAE announcement, May 22, 2025, with 200 MW expected in 2026.
Reliance Jio Jamnagar, gigawatt path, India
First phase about 120 MW due late 2026. Mukesh Ambani described a path to gigawatt-scale compute (February 19, 2026). A January 2025 Bloomberg report had described a 3 GW plan. This page uses the later official path language, not the 3 GW headline.
HUMAIN, 1.0 GW, Saudi Arabia
Official November 9, 2026 release says planned power infrastructure is designed to support up to 1 GW of IT capacity. A 3 GW by 2030 figure appears in press accounts but was not in that release, so it is not used here.
Envision Ulanqab, 2.0 GW, China
Envision official release, August 6, 2026, "designed to scale to over 2GW of capacity." Bloomberg, August 5, 2026, says the initial 120 MW phase is operating, with plans to scale to 2 GW. Epoch AI estimates about 118 MW of current IT power and 470 MW planned, a much smaller figure, so the 2.0 GW line is the company's planned campus scale, not Epoch's IT estimate. A later Envision post on November 3, 2026 described a planned capacity of 3 GW. This page uses the earlier, conservative official "over 2GW" figure from the commissioning announcement.
Figures not used
Other China lines were left out because the figures were too weak or were not a single campus: ByteDance 5 to 6 GW in Ulanqab (South China Morning Post, September 3, 2026, anonymous source, preliminary talks); Ulanqab's 15 GW committed total (Financial Times, October 8, 2026, unnamed executive, city-wide across 89 sites); Alibaba Zhangbei and Huawei Horinger (Epoch, well under 1 GW of IT); VNET Bayin Ulanqab (Epoch, 700 MW planned IT); DayOne's two Johor campuses (Epoch about 473 MW and 422 MW of IT each; 789 MW combined in service per DayOne's September 20, 2026 SEC filing, but that is two sites).
This page is the source list for the November 24, 2026 post. Figures are as published on the dates shown.
Photo on the chart and the preview card: Rsparks3, data center roof, November 23, 2025, CC0 1.0, via Wikimedia Commons.
The Monday Haul · free weekly email
Energy, industry, infrastructure and policy in one short email every Monday, including new factories and grid projects. Every item sourced and dated. More about the Haul