In Grimes County, Texas, SpaceX and Tesla plan a chip campus with more than 100 million square feet of manufacturing space. Here is why making chips takes so much room.
Updated November 22, 2026 · Numbers as published by each source on the date shown
Because the room where chips are made is only one floor of the building. Intel says one of its fabs holds 1,200 multimillion-dollar tools and 1,500 pieces of utility equipment, and three of its four levels exist to support the clean room. Those tools also need huge amounts of power, ultrapure water and gases, on floors built not to shake. In Grimes County, Texas, SpaceX and Tesla plan Terafab, with more than 100 million square feet of manufacturing space.
Most of a fab is there to support one clean room.
Photo: Intel Free Press, October 17, 2011, CC BY 2.0, via Wikimedia Commons. Cranes building Intel's D1X chip factory at the Ronler Acres campus in Hillsboro, Oregon. Figures: Intel, ASML and the Office of the Texas Governor.
Every big chip campus is really a small city of air handlers, water plants, gas plants and power lines built around one very clean room, and America is building several of them right now.
What fills a chip factory
Intel describes its fabs as 70-foot-tall buildings with four levels. Only one of them, the clean room, is where chips get made. The other three are there to keep it running.
The fan deck on top houses the systems that keep the clean room air free of particles and held at the right temperature and humidity. Intel says it is the tallest level of the fab.
The clean room holds more than 1,200 tools that turn pizza-size silicon wafers into hundreds of chips each. Intel says four American football fields could fit inside each fab's clean room. Workers wear head-to-toe “bunny suits,” which Intel has said help keep its clean rooms “10,000 times cleaner than a hospital operating room.”
The clean subfab below holds thousands of pumps, transformers and power cabinets, plus big pipes that carry gases, liquids, waste and exhaust to and from every tool.
The utility level at the bottom holds the electrical panels, the main pipes and ducts, and the chillers and compressors.
Add it up and Intel counts 1,200 multimillion-dollar tools and 1,500 pieces of utility equipment in one fab. Almost all of that building is there to serve what happens on one floor.
Some of the machines are as big as a bus
The most advanced tool in a modern fab prints the smallest chip patterns with extreme ultraviolet light, a method called EUV. ASML, the Dutch company that makes it, said in 2017 that one EUV system “weighs approximately 180,000 kilograms” and “ships in 40 freight containers, spread over 20 trucks and 3 cargo planes.”
The newest version is bigger still. When one arrived at the Albany NanoTech Complex in Albany, New York, in July 2026, Gov. Kathy Hochul's office said it “is as large as a double decker bus, weighs more than 200 tons, and arrives in 250 crates.” Intel added a support building at its research fab in Hillsboro, Oregon, with an elevator rated for 65,000 pounds, built to handle the heaviest parts of these machines. Floors, ceilings, doors and cranes all have to be sized around tools like these.
Power, water, gases and a floor that can't shake
The tools are only half of the building. The other half feeds them.
Power. “A large fab might demand 100 megawatts of energy,” Brian Potter wrote in Construction Physics. In Arizona, the utility APS estimates TSMC's whole north Phoenix campus would use about 1.9 gigawatts at full buildout, KJZZ reported, under a 25-year contract APS filed on November 6, 2026. The Arizona Corporation Commission still has to approve it. (For what a gigawatt figure measures, see what a 1-gigawatt data center really means.)
Ultrapure water. Fabs use “ultrapure” water to wash microscopic particles off the wafers, Axios explained. TSMC's first Phoenix factory uses about 4.75 million gallons a day, 65% of it recycled, Axios reported, citing the company. TSMC says a water reclamation plant “expected to be completed in 2028” will let the campus recycle 90% or more.
Gases. Fabs use so much nitrogen that they often have air separation plants on site, Construction Physics notes. Linde already runs three air separation units at its gas complex serving a major chipmaker in Phoenix, and on July 31, 2026 it said it will spend $1 billion on two more “to support two new semiconductor fabrication facilities.”
A floor that can't shake. The tools are so sensitive that, Construction Physics explains, fabs are built away from airports, rail lines and busy highways, and the clean room floor is “typically built as a deep concrete waffle slab two to four feet thick,” held up by closely spaced columns.
What it takes to build one
Intel says a fab “takes about three to four years, over $10 billion and 7,000 construction workers to complete.” For a pair of leading-edge fabs, it lists 58,000 tons of structural steel, which it calls “8X the weight of the Eiffel Tower,” plus 500,000 cubic meters of concrete and 23 million feet of cable.
Then the factory has to learn. TSMC chairman C.C. Wei said in April 2026 that after two to three years of building, “it takes another one to two years to ramp it up,” meaning the months of tuning before a new line turns out good chips in volume.
Get the free Monday Haul to follow the chip plants, power plants and lines being built in America, every week.
The Monday Haul · free weekly email
Energy, industry, infrastructure and policy in one short email every Monday, including new factories and grid projects. Every item sourced and dated. More about the Haul
Why chipmakers build whole campuses
Once the gas plant, the water plant and the power lines are in place, adding the next factory beside them is easier than starting over somewhere else. That is why the big projects in America are campuses.
TSMC's site in north Phoenix, Arizona, covers more than 1,100 acres, with plans underway for six chip factories, two advanced packaging plants and a research center (see whether leading-edge chips are being made on US soil). In Clay, New York, Micron plans four memory chip factories with 600,000 square feet of clean room each. The U.S. Commerce Department called the 2.4 million square feet total “the largest amount of cleanroom space ever announced in the United States.”
Terafab: the biggest plan yet
SpaceX and Tesla plan to build Terafab near Gibbons Creek Reservoir in Grimes County, Texas, about 20 miles east of College Station. Texas Gov. Greg Abbott announced it on August 6, 2026, saying “The first phase of the Terafab project represents a capital investment of more than $16.8 billion and will create 3,000 new jobs,” and that “The 100-million-square-foot facility will consolidate the production chain under a single roof.”
How big. Fortune noted that 100 million square feet is more than five times the New Century Global Center in Chengdu, China, which has about 18.9 million square feet. If it were all on one floor, it would cover about 2,300 acres, our math, or about twice the land of TSMC's whole Phoenix campus. Tom's Hardware points out that “100 million square feet of manufacturing space” does not mean that much clean room. The companies have not said how much clean room or how many tools it will hold.
What goes inside. State incentive filings describe one campus for chip design, photomask making, wafer making, advanced packaging and system assembly, “with supporting power generation and space compute test facility,” ENR reported. The filings say it would use “sub-2-nanometer-class semiconductor processes through partnerships with established manufacturers and equipment suppliers.”
Its own utilities. Under the county's tax deal, the plant is expected to run on “electricity generated by onsite power plants rather than the grid,” and the filings list gas turbines, utility-scale batteries, substations and gas and chemical lines. It plans to use surface water from Gibbons Creek Reservoir instead of groundwater, with on-site wastewater treatment and reuse.
Land. A company tied to the project, WIT TECH LLC, holds more than 10,000 acres in Grimes County, KBTX reported on November 10, 2026, citing appraisal records.
Timeline. The filings schedule the first phase for 2026 to 2028, with commercial operations expected in 2028, then possible phases in 2029 to 2031, 2032 to 2034 and 2035 to 2036. A county notice put the total at as much as $119 billion if every phase is built. The company's research fab is on the North Campus of Giga Texas in Austin, Texas. On Tesla's October 21, 2026 earnings call, Elon Musk said the first test chip there could come “around May or June” of 2027, and “our aspiration is to be making some kind of useful chip at volume around Q3 of 2028.”
Much is still open. SpaceX's IPO filing in May called Terafab a “general framework” with no binding commitments, Electrek reported, and the state filings say the company would decide after each phase whether to build the next. As of October, no lead architect or general contractor had surfaced publicly, ENR reported. What is confirmed is the place, the first-phase money and jobs, and crews at work: ENR reported that drone footage from October 6 shows “extensive earthwork and site preparation.”
Where people land
Four camps in the debate over giant chip campuses. Each camp gets the same space. This is not a poll, and the segments are not shares of support.
The question
How big should America build its chip plants?
Where they agree Every camp wants more of the world's chips made in the United States. They also agree the slow, hard part is everything around the clean room: power, water, skilled workers and time.
Go huge, all under one roof
Chips usually pass through different plants for logic, memory, packaging and testing, they say. Put every step on one campus and the waiting and shipping between steps shrink, and the chip demand coming from AI and robots needs a plant this size. Elon Musk said SpaceX is “combining logic, memory, and advanced packaging all under one roof.”
What they get right The biggest chipmakers already build in clusters. TSMC's Phoenix plan puts six chip factories, two packaging plants and a research center on one campus.
A chip factory is learned as much as it is built, they say. Getting good chips out of a new line takes years of tuning, so the fastest path to more American chips runs through companies that already know how. TSMC chairman C.C. Wei, asked about Terafab, said: “it takes two to three years to build a new fab. No shortcuts. And it takes another one to two years to ramp it up.”
What they get right Intel says even one fab takes about three to four years, over $10 billion and 7,000 construction workers to complete.
Big numbers are easy to announce, they say, so judge a project by signed contracts, permits and steel in the ground. The headline price has already moved, and the paperwork leaves room to stop after any phase. Electrek's Fred Lambert wrote: “So the confident tweet naming a county sits on top of a paper trail that says a lot of this is still undecided.”
What they get right SpaceX's IPO filing called Terafab a “general framework” with no binding commitments, and the state filings let the company decide after each phase whether to build the next.
Welcome the plant, they say, but put the roads, the water and the payback promises in writing before the tax breaks. A rural county should not carry the cost of a project this size. Bobbie Jo Swafford of Grimes County Citizens for Responsible Development said: “If they damage our roads, they're the ones paying to fix our roads.”
What they get right Nearly 900 residents signed the group's petition, and the county's road-use deal makes the company maintain six county roads during construction and repair the damage.
The building has already started Crews are already grading the Grimes County site, Texas A&M is putting up a chip training institute in nearby Bryan, and in north Phoenix TSMC's second factory is getting its tools. However big the next plants turn out to be, the work on them is already underway.
What to watch next
The first test chip at the Austin research fab, which Musk has pointed to for around mid 2027. Earthwork and the first buildings in Grimes County, and the court fight over which project records become public. Texas A&M's Semiconductor Institute building in Bryan, which its director says should be substantially complete by the end of 2027. The Arizona Corporation Commission's decision on the APS contract with TSMC, and 3-nanometer production at TSMC's second Phoenix factory in 2027. The Monday Haul follows these each week, and the Big Projects Map tracks the builds.
Common questions
How big is a chip factory?
Intel says each of its fabs is at least 250,000 square feet, and four American football fields could fit inside each fab's clean room. The building around it is about 70 feet tall with four levels. Micron's planned four-fab campus in Clay, New York, would have 2.4 million square feet of clean room, which the U.S. Commerce Department called the largest amount ever announced in the United States.
How many machines are in a chip factory?
Intel says one fab includes 1,200 multimillion-dollar tools and 1,500 pieces of utility equipment, such as pumps, chillers and power cabinets. One of the most advanced tools, ASML's EUV lithography machine, weighs about 180,000 kilograms and ships in 40 freight containers.
How much water and power does a chip factory use?
TSMC's first factory in north Phoenix, Arizona, uses about 4.75 million gallons of water a day, 65% of it recycled, Axios reported, citing the company. TSMC says a reclamation plant due in 2028 will let it recycle 90% or more. APS estimates the whole Phoenix campus would use about 1.9 gigawatts at full buildout, under a contract state regulators have not yet approved.
What is Terafab and where is it being built?
Terafab is a chip campus SpaceX and Tesla plan near Gibbons Creek Reservoir in Grimes County, Texas, about 20 miles east of College Station. Texas says the first phase is more than $16.8 billion and 3,000 jobs. The plan calls for more than 100 million square feet of manufacturing space, with on-site power plants. Elon Musk calls volume chip production around the third quarter of 2028 an aspiration.
Sources
Inside a fab
What does it take to build a fab?, Intel, 2022 fact sheet. 70-foot-tall structure, four levels, 1,200 tools, 1,500 pieces of utility equipment, three to four years, over $10 billion, 7,000 construction workers; steel, concrete and cable for a pair of fabs.
Intel: 'Sponsors of Tomorrow', Intel press release, May 6, 2009. Clean rooms “10,000 times cleaner than a hospital operating room.”
How to Build a $20 Billion Semiconductor Fab, Brian Potter, Construction Physics, May 3, 2024. About 100 megawatts for a large fab; waffle slab two to four feet thick; siting away from vibration.
TSMC Arizona, TSMC, accessed November 22, 2026. Reclamation plant expected to be completed in 2028, recycling 90% or more; more than 1,100 acres; six fabs, two packaging plants and an R&D center.
Preliminary terms with Micron, U.S. Department of Commerce, April 25, 2024. 600,000 square feet of clean room per fab, 2.4 million total in Clay, New York.
Takes Big Cranes to Build Cutting Edge Chip Fab, photograph by Intel Free Press, October 17, 2011, Wikimedia Commons, CC BY 2.0. Cranes building Intel's D1X fab at the Ronler Acres campus in Hillsboro, Oregon. Toned, cropped and overlaid with text for this page.