The transformer shortage sets the pace of building

Updated October 21, 2026 · Numbers as published by each source on the date shown

Large power transformers now take two to three years or more to arrive in the United States, up from about a year in 2020 and 2021. Demand from new power plants, factories, data centers and grid replacements grew faster than factories could. Makers are adding capacity. Nearly $1.8 billion in new transformer production for North America has been announced since 2023, and several new US plants are under way.

What a transformer does

A transformer raises or lowers the voltage of electricity. Power plants use generator step-up transformers to send their power onto high-voltage lines. Substations, and smaller transformers on poles and pads, step the voltage back down for homes and businesses. When transformers arrive late, the projects that need them wait. Long lead times have led to project delays and cancellations, Wood Mackenzie reports.

How long the wait is now

In the second quarter of 2025, power transformers took an average of 128 weeks from order to delivery, and generator step-up transformers 143 weeks, according to Wood Mackenzie's September 2025 study for American Clean Power. By the first quarter of 2026, step-up transformer waits had passed 160 weeks, Wood Mackenzie analyst Ben Boucher told Reuters.

Bar chart of US transformer lead times: power transformers 128 weeks and generator step-up transformers 143 weeks in the second quarter of 2025, and step-up transformers more than 160 weeks in the first quarter of 2026. New plants being built include Hitachi Energy in Virginia, 457 million dollars, and Eaton in South Carolina, 340 million dollars.
Sources: Wood Mackenzie (Sep 2025); Reuters (Jul 9, 2026); Hitachi Energy (Jun 29, 2026); Eaton (Feb 12, 2025)

Utilities feel it directly. Roseville Electric Utility in California used to order equipment about a year before a project. With large substation transformers now past a three-year wait, it buys equipment for projects it knows are coming five years in advance, its chief executive, Dan Beans, told Reuters.

Why demand jumped

Wood Mackenzie points to several drivers.

Why supply takes time to grow

Makers cite shortages of raw materials and skilled technical workers as limits on expanding, Wood Mackenzie reports. Copper wire for the windings has been a bottleneck, and prices for the special electrical steel inside rose by up to 20% over a couple of months in 2025.

How builders are working around it

Reuters reported each of these steps in July 2026.

The new factories coming online

The shortage is expected to ease. Wood Mackenzie projects the shortfall of generator step-up transformers to narrow from more than 700 units in 2025 to about 140 by 2030, as new factory capacity comes online and demand from new power plants levels off.

The Monday Haul tracks new factories and grid projects every week. Past issues are in the archive, and you can follow energy in every state on the live dashboard.

What to watch next

Common questions

How long does it take to get a power transformer?

Power transformers averaged 128 weeks from order to delivery in the second quarter of 2025, and generator step-up transformers 143 weeks, according to Wood Mackenzie. Step-up transformer waits passed 160 weeks by the first quarter of 2026, a Wood Mackenzie analyst told Reuters.

Why is there a transformer shortage?

Demand rose faster than factories could grow. US electricity use rose about 7% from 2019 to 2024 after a slight decline over the previous decade, much of the grid's equipment is old, and new power plants, factories and data centers all need transformers. Makers cite shortages of skilled workers and materials as limits on expanding.

When will the transformer shortage end?

Wood Mackenzie expects it to ease. It projects the shortage of generator step-up transformers to narrow from more than 700 units in 2025 to about 140 by 2030, as new factory capacity comes online and demand from new power plants levels off.

What is a generator step-up transformer?

It raises the voltage of electricity from a power plant so it can travel on high-voltage transmission lines.