Project tracker
Track your favorite projects
Big builds take years. Here you can follow each one step by step: funded, permitted, steel in the ground, first power. Every step links its source, and dates the owner hopes to hit are marked as targets.
My projects
Tap ☆ Track on any project and it will show up here with its latest step. Saved on this device only. No account, free.
All projects (61)
Alaska LNG
Glenfarne (75%) and the Alaska Gasline Development Corporation (25%) · North Slope to Nikiski, Alaska
LatestNov 6, 2026: First work slips to 2027
NextState decision on the pipeline lease · Possibly before Dec 7, 2026
Amazon Pennsylvania data center campuses
Amazon · Salem Township (Luzerne County) and Falls Township (Bucks County), Pennsylvania
LatestNov 3, 2026: Falls Township project under construction
NextState air permits for Falls Township · Pending
AWS Virginia data center campuses
Amazon Web Services · Louisa County and other sites, Virginia
LatestMay 21, 2026: Plan restated, $119 billion already spent
NextNew campuses built out by 2040 · By 2040

Bagdad copper mine expansion
Freeport-McMoRan · Bagdad, northwest Arizona
LatestNov 4, 2026: Board approves $4.5 billion expansion
NextEngineering, procurement and early works · Underway; about 20% of spending in 2027
BASF Geismar MDI expansion
BASF · Geismar, Louisiana
LatestNov 11, 2026: New plant opened
NextFull production rates · No date set
Big Rooter Power solar project, Twin Oaks
Panamint Capital · Robertson County, Texas
LatestNov 4, 2026: First $769 million of financing closed
NextBig Rooter East construction starts · Dec 2026 (company plan)
BlueOval Battery Park Michigan
Ford · Marshall, Michigan
LatestNov 18, 2026: First cells ship
NextBattery pack plant running · Spring 2027

BlueOval City (Tennessee Truck Plant)
Ford and SK On · Stanton, Tennessee
LatestDec 15, 2025: Plan switches to gas trucks
NextTruck production starts · 2029 (company plan)
BlueOval SK Battery Park, now Ford Energy Systems
Ford (Ford Energy) · Glendale, Kentucky
LatestNov 2026: Electrode trial runs done, orders filling
NextGrid battery production starts · Late 2027 (company target)

Boom Superpower Superfactory
Boom Supersonic · Centennial, Colorado
LatestOct 22, 2026: Superfactory unveiled, first core complete
NextFirst firing of the Sprint Core · Before Thanksgiving, Nov 26, 2026 (company target)
Chobani Allentown manufacturing campus
Chobani · Allentown area (Upper Macungie Township), Pennsylvania
LatestOct 21, 2026: Building addition gets preliminary approval
NextChobani production begins · 2027 (state estimate)

Coastal Virginia Offshore Wind
Dominion Energy · About 27 miles off Virginia Beach, Virginia
LatestOct 31, 2026: 45 turbines installed, 25 handed to operations
NextThird and final offshore substation energized · By end of 2026 (company target)
CP2 LNG
Venture Global · Cameron Parish, Louisiana
LatestNov 10, 2026: 24 of 36 modules on site
NextFirst LNG · Mid-2027

Fervo Cape Station
Fervo Energy · Beaver County, Utah
LatestNov 18, 2026: 105 MW transmission agreement with Longroad Energy
NextGeoBlocks 2 and 3 enter commercial service · By Jan 1, 2027 (company target)
GlobalFoundries Malta expansion (Fab 8.2)
GlobalFoundries · Malta, New York
LatestNov 13, 2026: Ground broken on Fab 8.2
NextFirst new fab comes online · 2029 (company target)
Google Central Ohio data centers
Google · New Albany, Columbus and Lancaster, Ohio
LatestNov 19, 2026: Google offers to pay for a grid upgrade
NextColumbus line upgrade in service · Late 2028 (if approved)

Google Oklahoma investment
Google · Stillwater and Pryor, Oklahoma
LatestNov 2026: Deal approved, then challenged
NextSupreme Court challenge to the power deal · Pending
Google South Carolina data center program
Google · Berkeley and Dorchester Counties, South Carolina
LatestMay 28, 2026: Google says it is on schedule
NextDorchester campuses start running · Later in 2026 (Google, May 2026)
Google Texas data center program
Google · Armstrong and Haskell Counties, Texas
LatestSep 28, 2026: Crusoe named as Armstrong developer
NextFirst Haskell building finishes · Late Aug 2027 (state filing target)
Honda new hybrid auto plant, Central Ohio
Honda · Union County, Ohio
LatestNov 10, 2026: County sets up the site district
NextConstruction start · Pending government approvals
Intel Ocotillo Fab 52 and Fab 62
Intel · Chandler, Arizona
LatestOct 2026: Fab 52 at full production, Fab 62 tools going in
NextFab 62 production · End of 2028

Intel Ohio One
Intel · New Albany, Licking County, Ohio
LatestOct 21, 2026: First major structural truss set
NextFab 1 construction complete · 2030 (company target)

Intel Oregon expansion, Hillsboro
Intel · Gordon Moore Park, Hillsboro, Oregon
LatestBy Dec 31, 2025: MSB2 frame done
NextMSB2 support building finished · No date set
Joliet Technology Center
Hillwood and PowerHouse Data Centers · Joliet, Will County, Illinois
LatestNov 5, 2026: Court documents show refused payment
NextFederal court fight with ComEd · Pending
Lambda Red Clay data center campus
Lambda · Lowndes County, Alabama
LatestNov 4, 2026: Campus announced
NextConstruction starts · Q1 2027 (company plan)
Mesabi Metallics mine and Iowa steel mill
Mesabi Metallics (Essar Group) · Nashwauk, Minnesota and Lee County, Iowa
LatestNov 11, 2026: Lee County votes yes
NextFirst pellets at Nashwauk · "In coming weeks" (company statement)
Meta Hyperion data center
Meta · Richland Parish, Louisiana
LatestNov 2026: Gas plant cost jumps
NextSeven more gas plants go to regulators · Dec 2026
Meta Mesa data center
Meta · Mesa, Arizona
LatestSep 2026: Investment figure now $1.2 billion
NextSecond phase opens · 2026 (Meta's expectation in Jan 2025)
Micron megafab, Clay
Micron · Clay, New York
LatestJul 9, 2026: First concrete poured
NextFab 1 first wafer output · Calendar 2030 (company expectation)
Micron memory fabs, Boise
Micron · Boise, Idaho
LatestJun 2026: Building up, second fab site being blasted
NextFirst wafers from Fab 1 · Mid 2027 (company target)
Microsoft second datacenter, Mount Pleasant
Microsoft · Mount Pleasant, Wisconsin
LatestOct 2026: Campus site plan amended
NextSecond datacenter complete · 2028 (Microsoft schedule)

Mon Valley hot strip mill
U.S. Steel (a Nippon Steel subsidiary) · Edgar Thomson Plant, Braddock, Pennsylvania
LatestNov 17, 2026: Written comments close
NextCounty air permit decision · No date set
Montana Renewables MaxSAF expansion, Great Falls
Calumet (Montana Renewables) · Great Falls, Montana
LatestNov 5, 2026: Equipment lease signed
NextTie in turnaround · Q4 2026
Nscale Monarch Compute Campus
Nscale · Near Point Pleasant, Mason County, West Virginia
LatestNov 13, 2026: Public comment closes
NextAir permit decision · No date set
OpenAI Project Camellia data center
OpenAI (Octans GA LLC) · Savannah Gateway Industrial Hub, Effingham County, Georgia
LatestNov 6, 2026: Second lawsuit seeks damages
NextEarlier lawsuit and county vote · Pending
Paducah American Energy Hub
Brookfield and NextEra Energy · Paducah Site, McCracken County, Kentucky
LatestAug 6, 2026: Kentucky sets data center rules
NextPower deal goes to state regulators · No date set
Pirelli Rome plant expansion
Pirelli · Rome, Georgia
LatestNov 10, 2026: Bond deal approved
NextCourt hearing to validate the bonds · Nov 30, 2026
Plaquemines LNG
Venture Global · Plaquemines Parish, Louisiana
LatestOct 31, 2026: Phase 1 enters commercial operation
NextPhase 2 commercial operation · Mid 2027 (company target)
Project Jupiter, Santa Teresa
STACK Infrastructure and BorderPlex Digital Assets, for Oracle and OpenAI · Santa Teresa, Dona Ana County, New Mexico
LatestNov 6, 2026: Air permit hearing canceled
NextAir permit hearing · No date set
Project Mica data center campus, Kansas City Northland
Google · Kansas City Northland, Missouri
LatestFeb 12, 2026: Google confirms it is building
NextFirst building finished · About 18 months after the start (Port KC)
Project Star energy campus
Related Companies, NextEra Energy Resources, Lewis Energy Group · Encinal, La Salle County, Texas
LatestOct 13, 2026: No permit filings found yet
NextFirst power · As early as 2029
Ridgeline Expansion pipeline
East Tennessee Natural Gas (Enbridge) · Trousdale County to Roane County, Tennessee
LatestNov 1, 2026: Gas starts flowing
NextKingston gas plant comes online · End of 2028
Rio Grande LNG
NextDecade · Port of Brownsville, Cameron County, Texas
LatestOct 2026: Pipeline in service, dredging done
NextFirst LNG from Train 1 · Q2 2027
Saronic Franklin shipyard
Saronic Technologies · Franklin, Louisiana
LatestNov 3, 2026: Second Marauder in the water
NextExpansion complete · Early 2027 (builder schedule)
Scout Motors plant, Blythewood
Scout Motors (Volkswagen) · Blythewood, South Carolina
LatestNov 12, 2026: Plant 85% complete, first test vehicles
NextSecond round of test builds · Early 2027
SK hynix packaging plant, West Lafayette
SK hynix · Purdue Research Park, West Lafayette, Indiana
LatestNov 16, 2026: Construction support site approved
NextRezoning trial · Dec 1, 2026
South32 Hermosa Taylor mine
South32 · Patagonia Mountains, Santa Cruz County, Arizona
LatestNov 6, 2026: Court lets work go on
NextFirst production · First half of 2028 (South32's second half of fiscal 2028)

SpaceX Florida Gigabay
SpaceX · Roberts Road, Kennedy Space Center, Florida
LatestOct 2026: Expansion goes to environmental review
NextBooster 23 and Ship 43 arrive from Starbase · No date set
SpaceX power plant and supercompute, Starbase
SpaceX · Starbase, Texas
LatestNov 12, 2026: SpaceX lays out the plan
NextTax abatement hearing · Dec 9, 2026
SpaceX supercompute campus, Cochise County
SpaceX · Near Willcox, Arizona
LatestNov 12, 2026: SpaceX announces the campus
NextPlanning and Zoning hearing · Dec 9, 2026
Starbase Louisiana
SpaceX · Vermilion Parish, near Pecan Island, Louisiana
LatestAug 25, 2026: SpaceX announces a $100 billion spaceport
NextCommunity town halls · "In the coming months" (no dates yet)
SunZia Wind and Transmission
Pattern Energy · Central New Mexico to south central Arizona
LatestJul 8, 2026: SRP signs for 600 MW
NextSRP takes its full 600 MW · Summer 2027
Terafab
SpaceX, with Tesla · Grimes County, Texas (research fab in Austin)
LatestOct 2026: Timetable laid out on earnings calls
NextFirst test chip at the Austin research fab · About May or June 2027 (company target)
Tesla Giga Nevada expansion
Tesla · Storey County (near Sparks), Nevada
LatestOct 2026: Volume production confirmed
NextFirst European Semi deliveries · By end of 2027 (company target)
Tesla polysilicon refinery, Robstown
Tesla · Near Robstown, Nueces County, Texas
LatestNov 18, 2026: Tax break application posted
NextTax deal review · No date set
Texas Instruments Sherman fabs
Texas Instruments · Sherman, Texas
LatestDec 17, 2025: SM1 starts production
NextSM2 fitted out and running · No date set

Thacker Pass lithium
Lithium Americas, with GM · Humboldt County, Nevada
LatestNov 11, 2026: Cost update, schedule holds
NextYear-end 2026 construction goals · By end of 2026 (company targets)

TSMC Arizona
TSMC · North Phoenix, Arizona
LatestOct 15, 2026: Fab 2 construction finished
NextFab 2 volume production · Q3 2027 (company target)
Valar Atomics Ward 250 and Raceway campus
Valar Atomics · Emery and Carbon counties, Utah
LatestNov 12, 2026: Raceway campus wins county permit
NextFederal and state permits for Raceway · No date set
Vantage Frontier data center campus
Vantage Data Centers · Shackelford County, Texas
LatestNov 20, 2026: Oracle says Shackelford is fully permitted
NextRack handover in the data halls · Coming weeks
xAI data center, Southaven
xAI (now part of SpaceX) · Southaven, DeSoto County, Mississippi
LatestNov 10, 2026: Permit board rejects appeal
NextFederal turbine lawsuit · Pending
Want the whole map? See Big Projects Map. Last checked Nov 22, 2026.