Plaquemines LNG
A 20 million tonne a year LNG export plant on the Mississippi below New Orleans.
Show on the map: Plaquemines LNG
- Financing$21 billion ($13.2 billion Phase 1, $7.8 billion Phase 2)Venture Global (DOE status report), Oct 2026
- Nameplate capacity20 million tonnes a yearVenture Global (DOE status report), Oct 2026
- Phase 1 commercial operationOct 31, 2026Venture Global, Nov 1, 2026
Next gate
Phase 2 commercial operation
Mid 2027 (company target)
Venture Global targets commercial operation of Phase 2 in mid 2027, with long-term Phase 2 deliveries by the end of the second quarter of 2027.
Every step so far, and what comes next
-
DoneAug 18, 2021
Construction starts
Construction of the export terminal began.
-
DoneMay 25, 2022
Phase 1 financed
Final investment decision and $13.2 billion of construction financing for the first 13.33 million tonne phase.
-
DoneMar 13, 2023
Phase 2 financed
Another $7.8 billion closed for the second phase, fully funding the 20 million tonne plant.
-
DoneDec 26, 2024
First commissioning cargo
The plant began making LNG in December 2024 and shipped its first commissioning cargo.
-
DoneOct 31, 2026
Phase 1 enters commercial operation
Venture Global declared commercial operations for Phase 1.
Source: Venture Global, Nov 1, 2026
-
ExpectedFirst half of 2027company target
Expansion investment decision
Subject to approvals, Venture Global targets a final investment decision on the Plaquemines expansion in the first half of 2027, with first LNG in 2029.
-
NextMid 2027company target
Phase 2 commercial operation
Phase 2 commercial operation is targeted for mid 2027.
Worth knowing
- The $21 billion is project financing, not a construction cost.
- The plant exported commissioning cargoes for almost two years before declaring commercial operation.
Last checked Nov 19, 2026. We add a step when it happens and link the source.