Project Jupiter, Santa Teresa
A four building AI data center campus near the Texas line, running on its own on site power plant.
Show on the map: Project Jupiter
- InvestmentAt least $50 billion in the first five years, up to $165 billion over 30 yearsDona Ana County, 2026
- ContractsMore than $994 million to 30 New Mexico firms (to Sep 30, 2026)Oracle, Oct 23, 2026
- Workers4,393 so far, 1,230 from New MexicoOracle, Oct 23, 2026
- Permanent jobsAt least 750 required within three years of openingDona Ana County, 2026
Next gate
Air permit hearing
No date set
The Dec 7 hearing on the power plant's air permit was canceled at the request of the state and the developer. It will be rescheduled after the state's Air Quality Bureau makes its recommendation.
Every step so far, and what comes next
-
DoneSep 19, 2025
County approves the bonds
Dona Ana County commissioners voted 4 to 1 to issue industrial revenue bonds for the project.
Source: El Paso Matters, Sep 19, 2025
-
DoneApr 2026
Power plan changed to fuel cells
Oracle announced a cleaner power plan built around fuel cells.
Source: Oracle, Oct 13, 2026
-
DoneOct 13, 2026
Economic impact estimate
Oracle said the campus should bring more than $13 billion in economic impact to New Mexico through construction and 17 years of operation.
Source: Oracle, Oct 13, 2026 · On X: post
-
DoneOct 23, 2026
Nearly $1 billion in local contracts
Oracle said more than $994 million in contracts had gone to New Mexico firms by Sep 30.
Source: Oracle, Oct 23, 2026
-
DoneNov 6, 2026
Air permit hearing canceled
A hearing officer vacated the Dec 7 hearing and waived the Nov 23 decision deadline. No new date was set.
-
NextNo date set
Air permit hearing rescheduled
The hearing will be reset after the Air Quality Bureau makes a recommendation.
-
ExpectedBy Q3 2028company target
First 400 acre phase complete
The county agreement expects the first phase, including the microgrid, done by the third quarter of 2028.
Source: Dona Ana County, 2026
Worth knowing
- The map counts the $50 billion minimum. The $165 billion is the most allowed over 30 years.
- Oracle says its job and investment figures assume the air permit and gas pipeline are approved.
- Construction has continued while the permit is pending.
Our posts on this build
Last checked Nov 21, 2026. We add a step when it happens and link the source.