Track your favorite projects · Data centers

Project Jupiter, Santa Teresa

STACK Infrastructure and BorderPlex Digital Assets, for Oracle and OpenAI · Santa Teresa, Dona Ana County, New Mexico

Under construction, air permit pending

A four building AI data center campus near the Texas line, running on its own on site power plant.

Show on the map: Project Jupiter

Next gate

Air permit hearing

No date set

The Dec 7 hearing on the power plant's air permit was canceled at the request of the state and the developer. It will be rescheduled after the state's Air Quality Bureau makes its recommendation.

Every step so far, and what comes next

  1. DoneSep 19, 2025

    County approves the bonds

    Dona Ana County commissioners voted 4 to 1 to issue industrial revenue bonds for the project.

  2. DoneApr 2026

    Power plan changed to fuel cells

    Oracle announced a cleaner power plan built around fuel cells.

  3. DoneOct 13, 2026

    Economic impact estimate

    Oracle said the campus should bring more than $13 billion in economic impact to New Mexico through construction and 17 years of operation.

  4. DoneOct 23, 2026

    Nearly $1 billion in local contracts

    Oracle said more than $994 million in contracts had gone to New Mexico firms by Sep 30.

  5. DoneNov 6, 2026

    Air permit hearing canceled

    A hearing officer vacated the Dec 7 hearing and waived the Nov 23 decision deadline. No new date was set.

  6. NextNo date set

    Air permit hearing rescheduled

    The hearing will be reset after the Air Quality Bureau makes a recommendation.

  7. ExpectedBy Q3 2028company target

    First 400 acre phase complete

    The county agreement expects the first phase, including the microgrid, done by the third quarter of 2028.

Worth knowing

Our posts on this build

Last checked Nov 21, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.