Track your favorite projects · Gas turbines
Boom Superpower Superfactory
An airplane company building 42 MW gas turbines for data centers, in its own factory.

- Investment$150 million, nearly 200,000 sq ftBoom Supersonic, Oct 22, 2026
- JobsUp to 500Boom Supersonic, Oct 22, 2026
- Output goal25 turbines (1 GW) a year by 2028, 50 (2 GW) by 2029 (company targets)Boom Supersonic, Oct 22, 2026
Next gate
First firing of the Sprint Core
Before Thanksgiving, Nov 26, 2026 (company target)
Boom's first prototype turbine core is on its test stand at Colorado Air and Space Port in Watkins. As of Nov 19, no firing had been announced.
Every step so far, and what comes next
-
DoneOct 22, 2026
Superfactory unveiled, first core complete
Boom unveiled the $150 million Superfactory, already making turbine parts as construction continues, and its first complete turbine core, Sprint Core, which shipped to its test site.
Source: Boom Supersonic, Oct 22, 2026 · On X: post, reply
-
NextBefore Nov 26, 2026company target
Sprint Core fires for the first time
The next major milestone, firing the core, is expected before Thanksgiving.
Source: Boom Supersonic, Oct 22, 2026
-
ExpectedEarly 2027company target
Factory fully operational
The factory is expected to be fully operational by early 2027.
Source: Boom Supersonic, Oct 22, 2026
-
ExpectedMid-2027company target
First customer deliveries
First Superpower turbine deliveries are targeted for mid-2027.
Source: Boom Supersonic, Oct 22, 2026
-
Expected2028 and 2029company target
25 turbines a year, then 50
Boom targets 1 GW (25 turbines) a year by 2028 and 2 GW (50 turbines) by 2029.
Source: Boom Supersonic, Oct 22, 2026
Worth knowing
- Delivery dates, jobs and production rates are Boom's own targets. Boom has not named its turbine customers.
Our posts on this build
- Post on: Superfactory unveiled, first core complete
- Follow-up reply on: Superfactory unveiled, first core complete
- Related post on X
Last checked Nov 19, 2026. We add a step when it happens and link the source.