Rio Grande LNG
NextDecade's LNG export plant at the Port of Brownsville, five trains under construction by Bechtel.
Show on the map: Rio Grande LNG Phase 1
- Phase 1 cost$18 billion including financing costs (map figure, from NextDecade's 10-Q)NextDecade, Oct 29, 2026
- Trains 1 and 279.7% complete in September 2026NextDecade, Oct 29, 2026
- CapacityTrains 1 to 5 uprated by FERC from 27 to 30.15 million tonnes a yearNextDecade, Oct 29, 2026
Next gate
First LNG from Train 1
Q2 2027
NextDecade expects first gas into the plant before the end of 2026 and first LNG from Train 1 in the second quarter of 2027.
Every step so far, and what comes next
-
DoneJul 12, 2023
Phase 1 final investment decision
NextDecade approved construction of the first phase.
Source: NextDecade, Jul 12, 2023
-
DoneSep 2026
Trains 1 and 2 at 79.7%
Engineering and procurement are nearly done; construction is 68.8% and commissioning 4.9%.
Source: NextDecade, Oct 29, 2026
-
DoneOct 2026
Pipeline in service, dredging done
The Bay Runner pipeline reached service and dredging finished.
Source: NextDecade, Oct 29, 2026
-
ExpectedBefore end of 2026
First gas into the plant
NextDecade expects first gas before year end.
Source: NextDecade, Oct 29, 2026
-
NextQ2 2027
First LNG from Train 1
The company's target; substantial completion in Q3 2027.
Source: NextDecade, Oct 29, 2026
Worth knowing
- The $18 billion includes financing costs, not just construction.
- Train 6 is not yet approved; NextDecade targets a final investment decision in the second half of 2027.
- Dates are company targets.
Last checked Nov 22, 2026. We add a step when it happens and link the source.