Track your favorite projects · LNG export
CP2 LNG
Venture Global's third Louisiana LNG export terminal, on the Calcasieu Ship Channel.
Show on the map: CP2 LNG
- Capacity29 million tonnes a year at peakVenture Global, Mar 13, 2026
- Financing$20.7 billion across both phases ($15.1 billion Phase 1, $8.6 billion Phase 2)Venture Global, Mar 13, 2026
- SalesNearly all capacity sold under long-term contracts, mostly to Europe and AsiaVenture Global, Mar 13, 2026
Next gate
First LNG
Mid-2027
EPC Feed reports the owner has 24 of 36 modules on site and targets first LNG in mid-2027.
Every step so far, and what comes next
-
DoneJun 27, 2024
FERC approves the terminal and pipeline
FERC issued its order authorizing CP2 LNG and the CP Express pipeline.
-
DoneJul 28, 2025
Phase 1 final investment decision
Venture Global closed $15.1 billion of financing and approved construction of Phase 1.
Source: Venture Global, Jul 28, 2025
-
DoneMar 13, 2026
Phase 2 final investment decision
Venture Global closed $8.6 billion of financing for Phase 2, bringing total financing to $20.7 billion.
Source: Venture Global, Mar 13, 2026
-
DoneNov 10, 2026
24 of 36 modules on site
EPC Feed recorded the owner's report of 24 of 36 modules on site.
Source: EPC Feed, Nov 10, 2026
-
NextMid-2027
First LNG targeted
The owner's current target for first LNG.
Source: EPC Feed, Nov 10, 2026
Worth knowing
- Financing is not the same as total project cost; the map counts the low end of Venture Global's $32.5 billion to $33.5 billion estimate.
- Opponents have appealed FERC's approval in the D.C. Circuit (as of Oct 2025).
- The module count and mid-2027 target come from EPC Feed's summary of a company report.
Last checked Nov 22, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.