Intel Ohio One

Intel · New Albany, Licking County, Ohio

Under construction

Two leading-edge chip fabs on 1,000 acres east of Columbus.

Satellite radar image of the Intel Ohio One campus on November 10, 2025.
Photo: Umbra via Wikimedia Commons, CC BY 4.0, Nov 10, 2025. Satellite radar image from Umbra; contrast stretched for visibility.

Show on the map: Ohio One

Next gate

Fab 1 construction complete

2030 (company target)

Intel slowed the schedule in 2025 to match demand and says it can speed up if customers need the capacity. Steel framing is going up now.

Progress

Every step so far, and what comes next

  1. Done2022

    Construction begins

    The site has been under continuous construction since 2022.

    Satellite radar image of the Intel Ohio One site in New Albany, Ohio, on July 23, 2023, early in construction.
    Photo: Umbra via Wikimedia Commons, CC BY 4.0, Jul 23, 2023. Satellite radar image from Umbra; contrast stretched for visibility.
  2. DoneLate 2024

    Fab goes vertical

    Intel finished the basement level of the fab and started the above-ground structure.

    Satellite radar image of the Intel Ohio One site on January 19, 2025, after the first fab had started to go vertical.
    Photo: Umbra via Wikimedia Commons, CC BY 4.0, Jan 19, 2025. Satellite radar image from Umbra; contrast stretched for visibility.
  3. DoneFeb 28, 2025

    Schedule reset

    Intel set Mod 1 completion for 2030 with operations in 2030 to 2031, and Mod 2 for 2031 with operations in 2032.

  4. DoneOct 21, 2026

    First major structural truss set

    Crews set the first major structural truss on the campus's first fab.

  5. Next2030company target

    Fab 1 construction complete

    Intel plans to complete Mod 1 construction in 2030.

  6. Expected2030 to 2031company target

    Fab 1 starts operations

    Operations are planned to begin between 2030 and 2031.

  7. Expected2031 and 2032company target

    Fab 2 built and running

    Mod 2 construction is planned to finish in 2031, with operations in 2032.

Worth knowing

Our posts on this build

Last checked Nov 19, 2026. We add a step when it happens and link the source.