Track your favorite projects · Data centers
Google Texas data center program
Google's biggest bet on any state: three new AI data center campuses across West Texas and the Panhandle.
Show on the map: Google Texas program
- Investment$40 billion through 2027Google, Nov 14, 2025
- New campusesOne in Armstrong County, two in Haskell CountyGoogle, Nov 14, 2025
- Power contractedMore than 6,200 MW of new generation and capacity in TexasGoogle, Nov 14, 2025
- Armstrong crewsMore than 5,500 skilled workers on site dailyCrusoe, Sep 28, 2026
Next gate
First Haskell building finishes
Late Aug 2027 (state filing target)
A state filing for the Journey 1A building at the north Haskell County site gives late August 2027 as the expected finish.
Every step so far, and what comes next
-
DoneJun 2025
Ground broken in Armstrong County
Crusoe, which is developing the Armstrong County campus for Google near Claude, says it broke ground in June 2025.
Source: Crusoe, Sep 28, 2026
-
DoneNov 14, 2025
$40 billion plan announced
Google said it will invest $40 billion in Texas through 2027, including new campuses in Armstrong and Haskell Counties. One Haskell site will sit next to a new solar and battery plant.
Source: Google, Nov 14, 2025
-
DoneNov 2025
Construction starts in Haskell County
Google says construction began in Haskell in November 2025.
Source: Google, 2026
-
DoneApr 1, 2026
First Journey building started
A Google linked company told Texas regulators that the 285,280 square foot Journey 1A building in north Haskell County started construction on April 1, 2026.
Source: DatacenterDynamics, Jul 8, 2026
-
DoneSep 28, 2026
Crusoe named as Armstrong developer
Crusoe said it is building the Armstrong County campus for Google, wired directly to the Goodnight wind farms, with more than 5,500 workers on site each day.
Source: Crusoe, Sep 28, 2026
-
NextLate Aug 2027company target
Journey 1A finish
The state filing targets late August 2027 for the first Journey building.
Source: DatacenterDynamics, Jul 8, 2026
-
ExpectedThrough 2027company target
Investment period ends
Google framed the $40 billion as spending through 2027.
Source: Google, Nov 14, 2025
Worth knowing
- The $40 billion covers three new campuses, more work at Google's existing Ellis County sites, energy programs and training through 2027. It is not the cost of one site.
- Completion dates come from state construction filings by Google linked companies, not from Google announcements.
- The map shows the whole program at one pin in Haskell County.
Last checked Nov 20, 2026. We add a step when it happens and link the source.