Terafab

SpaceX, with Tesla · Grimes County, Texas (research fab in Austin)

Announced, research fab gearing up

Logic, memory and advanced packaging under one roof, at a scale no chip plant has tried.

Show on the map: Terafab

Next gate

First test chip at the Austin research fab

About May or June 2027 (company target)

Musk said machinery commissioning starts in the first half of 2027, with a first test chip around May or June, just to see if the line can make any chip at all. He called the timetable very aggressive.

Every step so far, and what comes next

  1. DoneAug 6, 2026

    Texas announces Terafab

    Governor Abbott announced a vertically integrated SpaceX chip plant in Grimes County, more than $16.8 billion for the first phase, with a $30 million Texas Enterprise Fund grant.

  2. DoneOct 2026

    Timetable laid out on earnings calls

    On the October earnings calls, Musk said the Austin research fab is progressing quickly, with a first test chip targeted for mid-2027 and volume production around Q3 2028.

  3. NextAbout May or June 2027company target

    First test chip

    Machinery commissioning at the Austin research fab is planned for the first half of 2027, then a first test chip around May or June, to prove the line can make a chip at all.

  4. ExpectedAbout Q3 2028company target

    Useful chips at volume

    The stated aspiration is a useful chip at volume around the third quarter of 2028.

Worth knowing

Our posts on this build

Last checked Nov 19, 2026. We add a step when it happens and link the source.