Valar Atomics Ward 250 and Raceway campus
A startup reactor that went critical in Utah, and a plan to scale it into a gigawatt campus.
Show on the map: Ward 250 test reactor · Raceway Energy Campus
- Ward 250 costNearly $1.3 billion, per state incentive documentsSalt Lake Business Journal, Aug 8, 2026
- Raceway campus640 acres; gas plant first, then 40 to 120 reactors, about 3 GWThe Salt Lake Tribune, Nov 13, 2026
- Ward 250 jobs275 over 10 yearsSalt Lake Business Journal, Aug 8, 2026
Next gate
Federal and state permits for Raceway
No date set
The county permit is not a reactor license. Raceway still needs an NRC construction permit, a Utah air permit and county building permits, plus three public meetings before building permits.
Every step so far, and what comes next
-
DoneSep 2025
Ground broken at San Rafael Energy Lab
Valar began building Ward 250 and an on-site TRISO fuel facility near Orangeville.
-
DoneJun 18, 2026
Ward 250 goes critical
The first DOE-authorized reactor built outside a national lab reached zero-power criticality under the Reactor Pilot Program.
-
DoneJul 1, 2026
First electricity
After power ascension, Ward 250 generated electricity and briefly ran a live website.
-
DoneNov 12, 2026
Raceway campus wins county permit
The Carbon County Planning Commission approved a conditional-use permit 4 to 1, with 26 conditions.
Source: The Salt Lake Tribune, Nov 13, 2026 · On X: post
-
NextNot scheduled
NRC and state permits for Raceway
An NRC construction permit, a state air permit and county building permits are still needed. No dates are published.
Worth knowing
- Raceway has no announced dollar figure.
- A county conditional-use permit is not an NRC construction permit.
- Ward 250 is a 100 kWt test reactor; Valar's commercial target is up to 5 MWe per unit.
Our posts on this build
Last checked Nov 19, 2026. We add a step when it happens and link the source.