GlobalFoundries Malta expansion (Fab 8.2)

GlobalFoundries · Malta, New York

Ground broken on Fab 8.2

A second chip fab beside GlobalFoundries' flagship plant, paid for by Japan and run by GF.

Show on the map: Malta campus

Next gate

First new fab comes online

2029 (company target)

GlobalFoundries expects the first new Malta fab to come online in 2029. A second fab of about the same size has no published date.

Every step so far, and what comes next

  1. DoneOct 2026

    $2 billion TSMC interposer deal

    GF agreed to make silicon interposers in Malta for TSMC's advanced packaging, ramping in the first half of 2028.

  2. DoneOct 14, 2026

    Picked to run two Japan-funded fabs

    GF was selected as technology provider and operator for two new Malta fabs under a US and Japan initiative of up to $21 billion.

  3. DoneNov 13, 2026

    Ground broken on Fab 8.2

    Construction started on the roughly $10 billion fab, part of a $12.3 billion New York expansion with more than 1,100 new jobs.

  4. ExpectedFirst half of 2028company target

    Interposer production ramps

    Volume production of TSMC interposers is expected to begin ramping in the first half of 2028.

  5. Next2029company target

    First new fab online

    The first new fab is expected to come online in 2029.

Worth knowing

Our posts on this build

Last checked Nov 19, 2026. We add a step when it happens and link the source.