BlueOval Battery Park Michigan
Ford's own LFP battery cell plant, making cells for a $28,350 electric pickup.
Show on the map: Marshall battery park
- Investment$3.5 billion announced in 2023; about $3 billion now reportedCNBC, Nov 18, 2026
- Capacity40 cells a minute, about 20 GWh a yearCNBC, Nov 18, 2026
- Jobs1,700 planned; about 800 hired so farMLive, Nov 18, 2026
Next gate
Battery pack plant running
Spring 2027
Cells are shipping now. The pack plant on the same site is expected to be fully running in spring 2027, ahead of the Ford Fathom launch in late 2027.
Every step so far, and what comes next
-
DoneFeb 13, 2023
Plant announced
Ford announced a $3.5 billion LFP battery plant using CATL licensed technology.
Source: Ford, Feb 13, 2023
-
DoneOct 2026
Cell production starts
Ford said cell production began in October.
Source: CNBC, Nov 18, 2026
-
DoneNov 18, 2026
First cells ship
The first LFP prismatic cells left Marshall for Fathom prototypes at Louisville Assembly Plant.
Source: Ford, Nov 18, 2026
-
NextSpring 2027
Pack plant fully running
The battery pack plant is expected to be fully operational in spring 2027.
Source: MLive, Nov 18, 2026
-
ExpectedQ4 2027company target
Ford Fathom launch
The Fathom pickup, the first vehicle using these cells, is expected in the fourth quarter of 2027.
Source: CNBC, Nov 18, 2026
Worth knowing
- The plant uses battery technology licensed from China's CATL, which has drawn criticism from some lawmakers.
- Capacity was cut from up to 40 GWh in the original plan.
Last checked Nov 19, 2026. We add a step when it happens and link the source.