Track your favorite projects · Data centers

Nscale Monarch Compute Campus

Nscale · Near Point Pleasant, Mason County, West Virginia

Site work underway, air permit pending

An off grid AI campus on the Ohio River that makes all of its own power with Caterpillar gas generators.

Show on the map: Nscale Monarch campus

Next gate

Air permit decision

No date set

West Virginia's air quality division found the on site power plant can meet air rules and took public comment through Nov 13, 2026. It still has to answer comments and take final action on the permit.

Every step so far, and what comes next

  1. DoneApr 17, 2026

    Air permit application

    Monarch Cloud Campus applied to build an off grid power plant for the data center campus near the former Mason County Airport.

  2. DoneSep 3, 2026

    State certification

    West Virginia certified Phase 1 as a High Impact Data Center, a projected $69.2 billion investment needing about 2 GW.

  3. DoneSep 2026

    About 900 workers on site

    Civil work was underway and the site manager said vertical construction would start soon, with around 900 people working on the site and pipeline.

  4. DoneNov 13, 2026

    Public comment closes

    The state took written comments on the draft air permit until Nov 13, after a public meeting and a virtual hearing.

  5. NextNo date set

    Air permit decision

    The air quality division answers comments and takes final action on the permit.

Worth knowing

Last checked Nov 21, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.