Google Central Ohio data centers
Three Google data center campuses around Columbus, and now Google paying to rewire the power lines that feed them.
Show on the map: Google Central Ohio (2024 commitment)
- 2024 commitment$2.3 billion across the three sitesGoogle, Jun 18, 2024
- Total in OhioMore than $20 billion since 2019 (Google)Google Cloud Press Corner, Nov 19, 2026
- JobsMore than 3,000 direct and supplier jobs in Ohio (2025)Google Cloud Press Corner, Nov 19, 2026
- Grid upgrade$10.8 million, paid by Google, for 15.5 miles of new conductorsGoogle Cloud Press Corner, Nov 19, 2026
Next gate
Columbus line upgrade in service
Late 2028 (if approved)
Google and Ohio Power asked state regulators to approve swapping 50 year old wires for higher capacity conductors. If the Public Utilities Commission of Ohio and the Ohio Power Siting Board say yes, the lines are expected in service by late 2028.
Every step so far, and what comes next
-
Done2019
First Ohio data center started
Google broke ground on its first Ohio data center in New Albany.
Source: Google, Jun 18, 2024
-
Done2022
Columbus cloud region opens
Google Cloud opened its Columbus region, serving customers such as the State of Ohio and Nationwide.
Source: Google, Jun 18, 2024
-
DoneJun 18, 2024
$2.3 billion more for 2024
Google said it would invest $2.3 billion in Ohio that year across Columbus, Lancaster and New Albany.
Source: Google, Jun 18, 2024
-
DoneNov 19, 2026
Google offers to pay for a grid upgrade
Google and Ohio Power filed a plan for Google to fund $10.8 million of advanced conductors on 15.5 miles of Columbus lines, so 24 MW Google already contracted arrives about two years early.
-
NextLate 2028company target
Line upgrade in service
Expected in service by late 2028, pending state approval.
Worth knowing
- The map counts only the $2.3 billion 2024 commitment. Google's earlier Ohio spending and its planned Franklin Furnace campus in Scioto County are not in that figure.
- The 24 MW of earlier power and the 700 MW corridor figure are company estimates that depend on regulators and on the planned 765 kV buildout.
Last checked Nov 20, 2026. We add a step when it happens and link the source.