Track your favorite projects · Pipelines
Ridgeline Expansion pipeline
A 110 mile gas pipeline built to fuel TVA's new 1,500 MW gas plant at Kingston.
Show on the map: Ridgeline pipeline
- CostAbout $1.105 billion (company estimate)Pipeline & Gas Journal, Nov 2, 2026
- LengthAbout 110 miles of 30 inch pipe, plus a header and lateralPipeline & Gas Journal, Nov 2, 2026
- CapacityUp to 300,000 dekatherms a day, all contracted by TVAPipeline & Gas Journal, Nov 2, 2026
- CompressorNew Hartsville station with an 8 MW solar arrayPipeline & Gas Journal, Nov 2, 2026
Next gate
Kingston gas plant comes online
End of 2028
The TVA plant the pipeline feeds was about halfway built in October 2026 and is scheduled to start generating by the end of 2028. A federal appeals court let construction continue while TVA appeals a ruling against the plant.
Every step so far, and what comes next
-
DoneApr 2, 2025
FERC approval
FERC granted the certificate to build and operate the project.
-
DoneOct 7, 2025
Construction cleared
FERC authorized East Tennessee to start construction.
-
DoneOct 30, 2026
Cleared to start service
FERC staff authorized the pipeline to go into service after field inspections of the route.
Source: Pipeline & Gas Journal, Nov 2, 2026 · On X: post
-
DoneNov 1, 2026
Gas starts flowing
East Tennessee told FERC the project began service on Nov 1.
Source: FERC eLibrary, Nov 3, 2026
-
NextEnd of 2028company target
Kingston gas plant online
TVA's 1,500 MW Kingston gas plant is scheduled to begin generating by the end of 2028.
Worth knowing
- The cost is the company's estimate, not a final figure.
- A lower court vacated TVA's environmental review for the Kingston gas plant; the appeal is pending.
- The map pin is at the Hartsville compressor area; the line crosses eight counties.
Our posts on this build
Last checked Nov 21, 2026. We add a step when it happens and link the source.