Big Rooter Power solar project, Twin Oaks

Panamint Capital · Robertson County, Texas

West phase under construction, East phase next

About 2 million American made solar panels going onto reclaimed coal mine land halfway between Dallas and Houston.

Show on the map: Big Rooter Power

Next gate

Big Rooter East construction starts

Dec 2026 (company plan)

Panamint expects to start building the 658 MWdc East phase in December 2026, with its share of the green loan expected to close in the first quarter of 2027.

Every step so far, and what comes next

  1. DoneJul 2026

    Construction starts on Big Rooter West

    Panamint says work on the 491 MWdc West phase began in July 2026.

  2. DoneJul 23, 2026

    Groundbreaking announced

    Panamint said it had broken ground on what it calls the largest solar build at an existing coal mine site in North America, with SOLV Energy as the builder.

  3. DoneNov 4, 2026

    First $769 million of financing closed

    Panamint closed the first phase of a $1.8 billion green loan to pay for building Big Rooter West.

  4. NextDec 2026company target

    East phase construction starts

    Construction on the 658 MWdc East phase is expected to begin.

  5. ExpectedQ1 2027company target

    East phase financing closes

    The over $1 billion second phase of the loan is expected to close.

  6. ExpectedAug 2028company target

    Big Rooter West online

    West is on track for commercial operation in August 2028.

  7. ExpectedAug 2029company target

    Big Rooter East online

    East is expected in commercial operation in August 2029.

Worth knowing

Our posts on this build

Last checked Nov 20, 2026. We add a step when it happens and link the source.