Coastal Virginia Offshore Wind
176 turbines going up off Virginia Beach, set to be the largest US offshore wind farm.

Show on the map: Coastal Virginia Offshore Wind
- Size2.6 GW, 176 turbines of 14.7 MWDominion Energy, Nov 1, 2026
- Budget$11.65 billion including contingencyThe Motley Fool, Oct 30, 2026
- ProgressAbout 85% complete (Q3 2026)The Motley Fool, Oct 30, 2026
Next gate
Third and final offshore substation energized
By end of 2026 (company target)
All three substations are installed. Dominion expects the last one to be energized by year end, while turbine installation continues.
Every step so far, and what comes next
-
DoneFeb 2024
Offshore construction begins
Work started offshore with the relocation of munitions and explosives of concern.
Source: Dominion Energy, Nov 1, 2026
-
DoneMay 2024
Foundation installs begin
Monopile foundation installation began.
Source: Dominion Energy, Nov 1, 2026
-
DoneOct 2025
All monopiles installed
Monopile installation finished, ending pile driving.
Source: Dominion Energy, Nov 1, 2026
-
DoneJan 2026
First turbine erected
The installation vessel Charybdis set the first turbine.
Source: Dominion Energy, Nov 1, 2026
-
DoneMar 2026
First power to the grid
CVOW delivered its first power to Virginia's grid.
Source: Dominion Energy, Nov 1, 2026
-
DoneOct 30, 2026
44 turbines up, 85% complete
Dominion reported 44 turbines installed, more than 640 MW, with the 45th going in.
Source: The Motley Fool, Oct 30, 2026 · On X: post
-
DoneOct 31, 2026
45 turbines installed, 25 handed to operations
All 176 foundations and transition pieces are complete.
Source: Dominion Energy, Nov 1, 2026
-
NextEnd of 2026company target
Final offshore substation energized
Dominion expects to energize the third and final offshore substation by year end.
Source: The Motley Fool, Oct 30, 2026
-
ExpectedEnd of 2027company target
Project complete
Dominion continues to expect completion by the end of 2027.
Source: The Motley Fool, Oct 30, 2026
Worth knowing
- Turbine installs slowed in September and October due to weather and vessel maintenance. Dominion says the delay is within its schedule contingency.
Our posts on this build
Last checked Nov 19, 2026. We add a step when it happens and link the source.