Track your favorite projects · Offshore wind

Coastal Virginia Offshore Wind

Dominion Energy · About 27 miles off Virginia Beach, Virginia

Under construction, already sending power

176 turbines going up off Virginia Beach, set to be the largest US offshore wind farm.

The Coastal Virginia Offshore Wind pilot turbines in the Atlantic off Virginia, photographed from the air.
Photo: BOEM-OPA via Wikimedia Commons, CC BY-SA 2.0, Jun 8, 2022. Pilot project turbines, June 2022. A clearly licensed photo of later commercial construction was not available.

Show on the map: Coastal Virginia Offshore Wind

Next gate

Third and final offshore substation energized

By end of 2026 (company target)

All three substations are installed. Dominion expects the last one to be energized by year end, while turbine installation continues.

Every step so far, and what comes next

  1. DoneFeb 2024

    Offshore construction begins

    Work started offshore with the relocation of munitions and explosives of concern.

  2. DoneMay 2024

    Foundation installs begin

    Monopile foundation installation began.

  3. DoneOct 2025

    All monopiles installed

    Monopile installation finished, ending pile driving.

  4. DoneJan 2026

    First turbine erected

    The installation vessel Charybdis set the first turbine.

  5. DoneMar 2026

    First power to the grid

    CVOW delivered its first power to Virginia's grid.

  6. DoneOct 30, 2026

    44 turbines up, 85% complete

    Dominion reported 44 turbines installed, more than 640 MW, with the 45th going in.

  7. DoneOct 31, 2026

    45 turbines installed, 25 handed to operations

    All 176 foundations and transition pieces are complete.

  8. NextEnd of 2026company target

    Final offshore substation energized

    Dominion expects to energize the third and final offshore substation by year end.

  9. ExpectedEnd of 2027company target

    Project complete

    Dominion continues to expect completion by the end of 2027.

Worth knowing

Our posts on this build

Last checked Nov 19, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.