BlueOval SK Battery Park, now Ford Energy Systems
A twin EV battery campus being retooled to build grid batteries for utilities and data centers.
Show on the map: Glendale campus
- Original investment$5.8 billion (2021 Ford and SK joint venture)Kentucky Cabinet for Economic Development, Sep 28, 2021
- New planLFP cells, storage modules and 20-foot DC containers, about 20 GWh a yearFord Authority, Nov 2026
- OrdersContracts and late-stage talks cover more than 80% of 2028 capacityFord Authority, Nov 2026
Next gate
Grid battery production starts
Late 2027 (company target)
Ford Energy says the Glendale plant remains on track to begin production in late 2027.
Every step so far, and what comes next
-
DoneSep 28, 2021
Twin battery plants announced
Kentucky announced a $5.8 billion Ford and SK battery campus in Glendale.
Source: Kentucky Cabinet for Economic Development, Sep 28, 2021
-
DoneDec 15, 2025
Ford takes over, plans grid storage
Under the joint venture split, Ford takes sole ownership of both Kentucky plants and plans to convert the site to battery energy storage systems.
Source: Ford (SEC filing), Dec 15, 2025
-
DoneNov 2026
Electrode trial runs done, orders filling
Ford Energy said it completed trial runs of electrode mixing and has more than 80% of 2028 capacity under contract or late-stage talks.
Source: Ford Authority, Nov 2026
-
NextLate 2027company target
Production starts
Production is targeted for late 2027.
Source: Ford Authority, Nov 2026
Worth knowing
- The $5.8 billion is the 2021 figure.
- The second Glendale plant never produced a battery and is being marketed to other users.
Last checked Nov 19, 2026. We add a step when it happens and link the source.