Meta Mesa data center

Meta · Mesa, Arizona

First two buildings serving traffic, three more under construction

A five building Meta campus in the East Valley: two buildings running, three more going up.

Show on the map: Meta Mesa data center

Next gate

Second phase opens

2026 (Meta's expectation in Jan 2025)

When the first buildings went live, Meta said the second phase of three buildings would likely open in 2026. Meta has not yet said they are running.

Every step so far, and what comes next

  1. DoneAug 2021

    Ground broken

    Meta started building its Mesa data center in August 2021.

  2. DoneMay 2022

    Three more buildings added

    Meta grew the plan to five buildings and more than 2.5 million square feet, raising its Arizona investment past $1 billion.

  3. DoneJan 30, 2025

    First two buildings online

    Meta said the Mesa data center is serving traffic. The first two buildings are running and three more are being built.

  4. DoneSep 2026

    Investment figure now $1.2 billion

    Meta's current Mesa fact sheet lists $1.2 billion of data center investment in Arizona.

  5. Next2026company target

    Second phase opens

    Meta said in January 2025 that the three remaining buildings would likely open in 2026.

Worth knowing

Last checked Nov 20, 2026. We add a step when it happens and link the source.