Track your favorite projects · Data centers

Google South Carolina data center program

Google · Berkeley and Dorchester Counties, South Carolina

Berkeley campus expanding, two Dorchester campuses under construction

Google growing its oldest Lowcountry campus and finishing two new ones in Dorchester County.

Show on the map: Google SC campuses

Next gate

Dorchester campuses start running

Later in 2026 (Google, May 2026)

At a May 2026 meeting in St. George, Google said it was on schedule and expected parts of both Dorchester County data centers to be running later in 2026, with construction going on for a couple more years.

Every step so far, and what comes next

  1. Done2007

    Berkeley County campus opens

    Google's first South Carolina data center opened in Berkeley County and has been expanded several times.

  2. DoneSep 26, 2024

    Dorchester County groundbreaking

    Google held a groundbreaking for its new Dorchester County data centers.

  3. DoneOct 13, 2025

    $9 billion announced

    Google said it will invest $9 billion in South Carolina through 2027 to expand Berkeley County and keep building the two Dorchester sites.

  4. DoneMay 28, 2026

    Google says it is on schedule

    At a packed community meeting in St. George, Google said both Dorchester projects were on schedule.

  5. NextLater in 2026company target

    First Dorchester buildings running

    Google expected parts of the two campuses to be operational later in 2026.

  6. ExpectedThrough 2027company target

    Investment period ends

    Google framed the $9 billion as spending through 2027.

Worth knowing

Last checked Nov 20, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.