Track your favorite projects · EVs and batteries
Tesla Giga Nevada expansion
Tesla's first factory built just for the Semi, plus a giant 4680 cell plant.
Show on the map: Giga Nevada
- InvestmentMore than $3.6 billion for two new factoriesReuters, Jan 24, 2023
- Semi capacity25,000 trucks a year installed; 50,000 a year plannedYahoo Finance, Oct 2026
- JobsMore than 3,000 during the Semi rampCNBC, Sep 24, 2026
Next gate
First European Semi deliveries
By end of 2027 (company target)
Tesla plans European customer demos in the first half of 2027 and first deliveries by the end of 2027, with those trucks built in Nevada.
Every step so far, and what comes next
-
DoneJan 24, 2023
Two new factories announced
Tesla said it would invest more than $3.6 billion in a 100 GWh 4680 cell plant and a high volume Semi factory.
Source: Reuters, Jan 24, 2023
-
DoneApr 29, 2026
First Semi off the high volume line
Tesla posted that the first truck had come off the new line.
Source: Reuters, Apr 29, 2026
-
DoneSep 24, 2026
Semi factory opens
Tesla held the ribbon cutting and said the plant is built for 50,000 trucks a year.
Source: CNBC, Sep 24, 2026 · On X: post
-
DoneOct 2026
Volume production confirmed
Tesla's third quarter report listed 25,000 Semis of installed yearly capacity in Nevada.
Source: Yahoo Finance, Oct 2026
-
NextBy end of 2027company target
First European deliveries
Tesla targets first European customer deliveries of the Semi by the end of 2027.
Source: Yahoo Finance, Oct 2026
Worth knowing
- Tesla has not said how many Semis it is building now.
- The 4680 cell plant status was not rechecked for this page.
Our posts on this build
Last checked Nov 19, 2026. We add a step when it happens and link the source.