Meta Hyperion data center

Meta · Richland Parish, Louisiana

Under construction, expanding to 5 GW

Meta's biggest AI training campus, on a former farm megasite between Rayville and Delhi.

Show on the map: Meta Hyperion data center

Next gate

Seven more gas plants go to regulators

Dec 2026

Entergy Louisiana plans to ask the Public Service Commission in December to approve seven more gas plants and new power lines for the campus.

Every step so far, and what comes next

  1. DoneDec 2024

    Project announced, ground broken

    Meta announced the Richland Parish data center and broke ground the same month.

  2. DoneAug 2025

    First three gas plants approved

    The Louisiana Public Service Commission approved Entergy's plan for three gas plants to serve the data center.

  3. DoneJul 13, 2026

    Expanded to 5 GW and $50 billion

    Meta grew the campus to 5 GW of computing and more than $50 billion, with a new Entergy deal for seven more gas plants and three big batteries.

  4. DoneNov 2026

    Gas plant cost jumps

    Entergy's quarterly report put the Waterford 5 plant at $1.755 billion, up from $1.079 billion.

  5. NextDec 2026

    Seven more gas plants go to regulators

    Entergy plans to seek approval for seven more gas plants and transmission lines.

Worth knowing

Last checked Nov 21, 2026. We add a step when it happens and link the source.