SunZia Wind and Transmission

Pattern Energy · Central New Mexico to south central Arizona

Fully operational since June 2026

The biggest clean power build in US history: a giant New Mexico wind farm and a 550 mile line to carry it west.

Show on the map: SunZia Wind and Transmission

Next gate

SRP takes its full 600 MW

Summer 2027

Salt River Project signed for 600 MW of SunZia wind. The deal set 400 MW starting this fall, rising to 600 MW by summer 2027.

Every step so far, and what comes next

  1. DoneSep 2023

    Construction begins

    Pattern says building started in September 2023. Senator Heinrich called the finish a milestone more than 18 years in the making.

  2. DoneDec 27, 2023

    $11 billion financing closed

    Pattern closed the financing and began full construction of the line and the wind farm across Torrance, Lincoln and San Miguel Counties.

  3. DoneJun 18, 2026

    Fully operational

    Pattern said SunZia is generating and delivering power from New Mexico to Arizona and the western grid.

  4. DoneJul 8, 2026

    SRP signs for 600 MW

    Arizona utility Salt River Project signed a power purchase agreement for 600 MW of SunZia wind.

  5. NextSummer 2027company target

    SRP steps up to 600 MW

    SRP's share rises to 600 MW by summer 2027.

Worth knowing

Our posts on this build

Last checked Nov 20, 2026. We add a step when it happens and link the source.