Joliet Technology Center
A 795 acre data center campus approved in Joliet, now stuck in a payment fight with ComEd.
Show on the map: Joliet Technology Center data center campus
- Size795 acres, up to 1.8 GW at full useShaw Local (The Herald-News), Nov 5, 2026
- Announced cost$20 billion (announced figure)Shaw Local (The Herald-News), Nov 5, 2026
Next gate
Federal court fight with ComEd
Pending
The developers sued in federal court to delay a $587 million grid security payment ComEd requires.
Every step so far, and what comes next
-
DoneMar 2026
Joliet City Council approves
The city approved the project after strong local opposition and union support.
-
DoneMay 2026
Dispute with ComEd begins
The disagreement over the grid payment started about two months after approval.
-
DoneNov 5, 2026
Court documents show refused payment
ComEd said developers refused to pay $587 million and sued to delay it.
-
NextPending
Court ruling
The federal case decides whether the payment is delayed.
Worth knowing
- ComEd said it is not apparent the developers have bought the land.
- The developers sent a $1 check instead of the $587 million.
- The $20 billion is an announced figure, not committed money.
- The city said the dispute does not involve it.
Last checked Nov 22, 2026. We add a step when it happens and link the source.