Saronic Franklin shipyard

Saronic Technologies · Franklin, Louisiana

Expansion under construction, ships launching

A closing boatyard turned into a line for autonomous ships.

Next gate

Expansion complete

Early 2027 (builder schedule)

The JE Dunn and Alberici team topped out the building in August. Saronic expects to reach full rate once the expansion is finished.

Every step so far, and what comes next

  1. Done2025

    Saronic buys the Gulf Craft yard

    Saronic bought the yard and its roughly 100-acre site while it was closing down.

  2. DoneAug 2025

    First Marauder keel laid

    Work began on the first 150-foot Marauder.

  3. DoneNov 2025

    Expansion construction begins

    Construction started on the $300 million expansion.

  4. DoneLate May 2026

    First Marauder launched

    The first Marauder went into the water less than a year after its keel was laid.

  5. DoneAug 13, 2026

    Expansion tops out

    Crews placed the final structural beam.

  6. DoneNov 3, 2026

    Second Marauder in the water

    The second hull took 8% fewer labor hours than the first and is running under its own power.

  7. NextEarly 2027company target

    Expansion complete

    The expansion is scheduled for completion in early 2027.

  8. ExpectedNo date set

    20 Marauders a year

    Fully ramped, Saronic says Franklin will build 20 Marauders a year.

Worth knowing

Our posts on this build

Last checked Nov 19, 2026. We add a step when it happens and link the source.