Alaska LNG

Glenfarne (75%) and the Alaska Gasline Development Corporation (25%) · North Slope to Nikiski, Alaska

Planning, no final investment decision yet

An 807 mile gas pipeline from the North Slope to an export terminal at Nikiski, with gas for Alaskans along the way.

Show on the map: Alaska LNG

Next gate

State decision on the pipeline lease

Possibly before Dec 7, 2026

The Alaska Department of Natural Resources proposed turning the project's conditional right of way lease into a full lease. Hearings are set for Nov 23 and 24 with comments through Nov 25, and a decision could come before Governor Dunleavy leaves office on Dec 7.

Every step so far, and what comes next

  1. DoneMar 2025

    Glenfarne takes the lead

    Glenfarne became lead developer and 75% owner, with the state gasline corporation keeping 25%.

  2. DoneJun 3, 2026

    Cost estimate to lawmakers

    Glenfarne told the Alaska Senate Finance Committee the full project would cost $44.5 billion to $54.5 billion.

  3. DoneSep 30, 2026

    Korean investment announced

    President Trump announced a South Korean investment of more than $50 billion in Alaska LNG. Glenfarne said it would work to finalize the structure.

  4. DoneNov 6, 2026

    First work slips to 2027

    Filings showed no construction in October. Early work on gravel pits, camp pads and pipe yards, once planned for April 2026, is now expected in 2027.

  5. NextPossibly before Dec 7, 2026

    State lease decision

    Natural Resources takes comments through Nov 25 and could decide on the full lease before the new governor takes office.

  6. Expected2029company target

    First gas

    The project's Oct 1 report to the Energy Department still targets pipeline completion in 2028 and first gas in 2029.

Worth knowing

Our posts on this build

Last checked Nov 21, 2026. We add a step when it happens and link the source.