Track your favorite projects · Semiconductors
Micron memory fabs, Boise
Two leading edge memory fabs going up beside Micron's headquarters.
Show on the map: Boise fabs
- First announced$15 billion for the first Idaho fab (2022)Micron, Sep 1, 2022
- Two fab planAbout $50 billion across both Boise fabsIdaho Statesman, Jun 2026
- JobsMore than 4,000 at Micron tied to the two fabsIdaho Statesman, Jun 2026
Next gate
First wafers from Fab 1
Mid 2027 (company target)
Micron expects first wafer output from the first new Boise fab in mid 2027 and from the second in late 2028.
Every step so far, and what comes next
-
DoneSep 1, 2022
First Idaho fab announced
Micron announced about $15 billion for a leading edge memory fab in Boise through the end of the decade.
Source: Micron, Sep 1, 2022
-
DoneJun 12, 2025
Second Boise fab added
Micron expanded its US plan, adding a second Idaho fab.
Source: Micron, Jun 12, 2025
-
DoneJun 2026
Building up, second fab site being blasted
On a May tour, Micron said the first fab stretches more than a third of a mile, with tool move-in planned later in 2026. Crews were blasting rock to level the second fab site.
Source: Idaho Statesman, Jun 2026
-
NextMid 2027company target
First wafers from Fab 1
First wafer output is expected in mid 2027.
Source: Micron, Jul 9, 2026
-
ExpectedLate 2028company target
First wafers from Fab 2
The second Boise fab is expected to reach first wafer output in late 2028.
Source: Idaho News 6, Sep 2026
Worth knowing
- The map counts the original $15 billion; Micron has since described about $50 billion across two Boise fabs.
- Dates are company targets.
Last checked Nov 19, 2026. We add a step when it happens and link the source.