Paducah American Energy Hub

Brookfield and NextEra Energy · Paducah Site, McCracken County, Kentucky

Announced, early studies

An AI data center campus and its own gas plants on leased land at the old Paducah uranium enrichment plant.

Show on the map: Paducah data center campus

Next gate

Power deal goes to state regulators

No date set

The power service agreement still needs approval from the Kentucky Public Service Commission. As of August 2026, no case tied to the project had been filed.

Every step so far, and what comes next

  1. DoneNov 2025

    Energy Department asks for offers

    The Energy Department asked companies to propose building and powering data centers on the Paducah Site.

  2. DoneJul 2026

    Brookfield and NextEra picked

    The Energy Department selected Brookfield to build and run the campus and NextEra to build and own its power plants.

  3. DoneAug 6, 2026

    Kentucky sets data center rules

    Governor Beshear ordered the Public Service Commission not to let utilities pass data center costs to other customers. No Paducah case was on file yet.

  4. NextNo date set

    State approval of the power deal

    The power service agreement must be approved by the Kentucky Public Service Commission.

  5. Expected2031company target

    Construction complete

    The Energy Department expects construction to be finished in 2031.

Worth knowing

Last checked Nov 21, 2026. We add a step when it happens and link the source.