Track your favorite projects · Data centers
Paducah American Energy Hub
An AI data center campus and its own gas plants on leased land at the old Paducah uranium enrichment plant.
Show on the map: Paducah data center campus
- Investment$100 billion (announced)U.S. Department of Energy, Aug 4, 2026
- Campus1.8 GW AI and high performance computing campus on about 785 leased acresU.S. Department of Energy, Aug 4, 2026
- Power2 GW of new gas generation and up to 2.6 GW of batteriesU.S. Department of Energy, Aug 4, 2026
- JobsAbout 8,000 construction, 600 permanentU.S. Department of Energy, Aug 4, 2026
Next gate
Power deal goes to state regulators
No date set
The power service agreement still needs approval from the Kentucky Public Service Commission. As of August 2026, no case tied to the project had been filed.
Every step so far, and what comes next
-
DoneNov 2025
Energy Department asks for offers
The Energy Department asked companies to propose building and powering data centers on the Paducah Site.
Source: NextEra Energy Resources, 2026
-
DoneJul 2026
Brookfield and NextEra picked
The Energy Department selected Brookfield to build and run the campus and NextEra to build and own its power plants.
-
DoneAug 6, 2026
Kentucky sets data center rules
Governor Beshear ordered the Public Service Commission not to let utilities pass data center costs to other customers. No Paducah case was on file yet.
Source: 270 Daily, Aug 8, 2026
-
NextNo date set
State approval of the power deal
The power service agreement must be approved by the Kentucky Public Service Commission.
-
Expected2031company target
Construction complete
The Energy Department expects construction to be finished in 2031.
Worth knowing
- The $100 billion is the announced total across all phases, not a signed contract.
- NextEra says the project is still in its early stages, with technical and environmental studies underway.
- The map pin is approximate, within the Paducah Site.
Last checked Nov 21, 2026. We add a step when it happens and link the source.