Thacker Pass lithium
Lithium clay from an ancient supervolcano lake, turned into battery-grade lithium carbonate.

- Phase 1 outputAbout 40,000 tonnes a year of lithium carbonateLithium Americas, Nov 11, 2026
- Phase 1 cost$3.83 billion (up from $2.93 billion)Lithium Americas, Nov 11, 2026
- WorkforceAbout 1,900 on site, heading to about 2,200Lithium Americas, Nov 11, 2026
Next gate
Year-end 2026 construction goals
By end of 2026 (company targets)
Lithium Americas aims to connect the site substation to the grid, finish all structural concrete foundations and the main field-erected tanks, and start early utility commissioning.
Progress

Photo: Umbra via Wikimedia Commons, CC BY 4.0, Jan 13, 2025. Satellite radar image from Umbra; contrast stretched for visibility.

Photo: Umbra via Wikimedia Commons, CC BY 4.0, Jun 21, 2025. Satellite radar image from Umbra; contrast stretched for visibility.
Every step so far, and what comes next
-
DoneApr 2025
Final investment decision
Lithium Americas declared the final investment decision on Phase 1.
Source: Lithium Americas, Nov 11, 2026
-
DoneAug 2026
All major structural steel delivered
All major structural steel reached the site by the end of August.
Source: Lithium Americas, Nov 11, 2026
-
DoneNov 11, 2026
Cost update, schedule holds
The company raised its Phase 1 estimate to $3.83 billion and kept mechanical completion on track for late 2027. Crews had logged 4.7 million work hours without a serious injury.
Source: Lithium Americas, Nov 11, 2026 · On X: post, reply
-
NextEnd of 2026company target
Grid hookup and foundations done
Connect the utility grid to the site substation, finish structural concrete foundations and begin early commissioning of utilities.
Source: Lithium Americas, Nov 11, 2026
-
Expected2027company target
Rail transload terminal complete
The transload terminal west of Winnemucca is targeted for completion in 2027.
Source: Lithium Americas, Nov 11, 2026
-
ExpectedLate 2027company target
Mechanical completion
Phase 1 construction is targeted to be mechanically complete in late 2027.
Source: Lithium Americas, Nov 11, 2026
-
Expected2028company target
Ramp-up to commercial production
Ramp-up to commercial production is expected through 2028.
Source: Lithium Americas, Nov 11, 2026
Worth knowing
- The Phase 1 cost estimate rose by $900 million in November 2026, citing labor, logistics and tariffs. The company says the added need is expected to be funded.