Track your favorite projects · Mining
South32 Hermosa Taylor mine
An underground zinc, lead and silver mine south of Tucson, the first mine at South32's Hermosa project.
Show on the map: Hermosa Taylor mine
- Growth spendingAbout $3.3 billion (from Jan 2024)South32, Apr 30, 2026
- Plant size4.3 million tonnes of ore a yearSouth32, Apr 30, 2026
- Mine lifeAbout 33 yearsSouth32, Apr 30, 2026
- Federal support$20 million (Defense Production Act) and $166.2 million (Energy Department)U.S. Department of Justice, Nov 10, 2026
Next gate
First production
First half of 2028 (South32's second half of fiscal 2028)
South32 expects first ore through the Clark decline in mid fiscal 2028 and first production in the second half of fiscal 2028, which runs January to June 2028. Full capacity is expected in fiscal 2031.
Every step so far, and what comes next
-
DoneFeb 15, 2024
Go ahead for Taylor
South32 approved $2.16 billion to build Taylor and then targeted first production in the second half of fiscal 2027.
Source: South32, Feb 15, 2024
-
DoneApr 30, 2026
Cost and schedule reset
South32 raised expected spending to about $3.3 billion and pushed first production to the second half of fiscal 2028, blaming slow shaft work by a contractor.
Source: South32, Apr 30, 2026
-
DoneJul 2026
Forest Service approval
The U.S. Forest Service approved the mine's expansion onto the Coronado National Forest for a road, a dry tailings site and a power line.
-
DoneNov 6, 2026
Court lets work go on
A federal judge denied environmental groups' request to halt the approved work while their lawsuit is decided. Work on private land is about half done.
Source: AZPM, Nov 10, 2026 · On X: post
-
NextFirst half of 2028company target
First production
First production is expected in the second half of South32's fiscal 2028.
Source: South32, Apr 30, 2026
-
ExpectedFiscal 2031company target
Full capacity
South32 expects nameplate production in fiscal 2031, which starts July 2030.
Source: South32, Apr 30, 2026
Worth knowing
- South32's fiscal year ends June 30, so its fiscal 2028 targets fall between July 2027 and June 2028.
- The cost rose from $2.16 billion at approval to about $3.3 billion, partly because shaft sinking ran slow.
- An environmental lawsuit over the federal land approvals is still being decided.
Our posts on this build
Last checked Nov 21, 2026. We add a step when it happens and link the source.