Scout Motors plant, Blythewood
The revived Scout brand building its Terra pickup and Traveler SUV in a new plant north of Columbia.
Show on the map: Scout Motors Blythewood
- InvestmentMore than $2 billionCNBC, Nov 12, 2026
- CapacityMore than 200,000 vehicles a year at full capacityOffice of the Governor of South Carolina, Mar 3, 2023
- Jobs4,000 at full capacity; about 900 in South Carolina nowSC Daily Gazette, Nov 13, 2026
- ReservationsAbout 212,000 for the Terra and TravelerCNBC, Nov 12, 2026
Next gate
Second round of test builds
Early 2027
Scout is finishing its first 30 to 40 test vehicles and plans a second round of testing in early 2027, with more phases through the year before full production.
Every step so far, and what comes next
-
DoneMar 3, 2023
Plant announced
Scout picked a Richland County site in Blythewood for a $2 billion plant with up to 4,000 jobs.
Source: Office of the Governor of South Carolina, Mar 3, 2023
-
DoneNov 2026
Validation builds in body and paint shops
Scout says robots are being tested and validation bodies are moving through the body shop and every stage of the paint process.
Source: Scout Motors, Nov 2026
-
DoneNov 12, 2026
Plant 85% complete, first test vehicles
CEO Scott Keogh said the plant is about 85% complete and the first round of test vehicles is nearly done.
Source: SC Daily Gazette, Nov 13, 2026 · On X: post
-
NextEarly 2027company target
Second round of test builds
A second round of testing starts in early 2027.
Source: SC Daily Gazette, Nov 13, 2026
-
Expected2027company target
Full production
The Terra and Traveler are expected to start full production in 2027.
Source: CNBC, Nov 12, 2026
-
Expected2028company target
First customer deliveries
Deliveries to customers are planned for 2028.
Source: CNBC, Nov 12, 2026
Worth knowing
- Production and delivery dates are company plans. Customer deliveries are now expected in 2028.
- Reservations are not orders.
- A $300 million supplier park is separate from the $2 billion plant.
Our posts on this build
Last checked Nov 20, 2026. We add a step when it happens and link the source.