SK hynix packaging plant, West Lafayette
The first US plant to stack and package the high bandwidth memory inside AI chips, next door to Purdue.
Show on the map: SK hynix West Lafayette
- Investment$4 billion (state figure); $3.87 billion at the 2024 launchIndiana Economic Development Corporation, Aug 27, 2026
- Plant430,000 square feet on 90 acresIndiana Economic Development Corporation, Apr 3, 2024
- JobsAbout 1,000 at full operationIndiana Economic Development Corporation, Aug 27, 2026
- OutputNext generation HBM memory for AI chipsIndiana Economic Development Corporation, Aug 27, 2026
Next gate
Rezoning trial
Dec 1, 2026
Three residents are challenging the 2025 rezoning under the site. A three day bench trial is set to begin Dec 1 in Tippecanoe Circuit Court. The ruling so far does not stop work.
Every step so far, and what comes next
-
DoneApr 3, 2024
Plant announced
SK hynix said it will invest about $3.87 billion in an HBM packaging and research plant at Purdue Research Park, with mass production planned for the second half of 2028.
Source: SK hynix, Apr 3, 2024
-
DoneAug 27, 2026
Ground broken
Governor Braun joined SK hynix to break ground on what the state now calls a $4 billion investment.
Source: Indiana Economic Development Corporation, Aug 27, 2026
-
DoneOct 22, 2026
Judge sends zoning case to trial
A Tippecanoe Circuit judge declined to end the residents' challenge before trial. The ruling does not stop construction.
Source: BusinessIndy, Oct 27, 2026
-
DoneNov 16, 2026
Construction support site approved
West Lafayette approved trailers, parking and laydown space at Site A for the construction crews.
-
NextDec 1, 2026
Rezoning trial begins
A three day bench trial on the rezoning is scheduled to start.
Source: BusinessIndy, Oct 27, 2026
-
ExpectedQ4 2028company target
Cleanroom opens
SK hynix expects to open the cleanroom by the fourth quarter of 2028.
Source: Indiana Economic Development Corporation, Aug 27, 2026
-
Expected2H 2029company target
Mass production
Mass production is planned for the second half of 2029.
Source: Indiana Economic Development Corporation, Aug 27, 2026
Worth knowing
- Cleanroom and production dates are company targets. The start of mass production has already slipped from the second half of 2028 to the second half of 2029.
- The rezoning lawsuit is still open.
Last checked Nov 20, 2026. We add a step when it happens and link the source.