Texas Instruments Sherman fabs

Texas Instruments · Sherman, Texas

SM1 producing, SM2 shell built

A site for up to four big chip fabs north of Dallas, making the basic chips that go into almost every device.

Show on the map: TI Sherman fabs

Next gate

SM2 fitted out and running

No date set

The SM2 building shell is finished. TI says its Sherman fabs will be built and equipped in line with market demand and has not given a production date for SM2.

Every step so far, and what comes next

  1. DoneMay 18, 2022

    Ground broken

    TI broke ground on the Sherman site, planned for up to four connected fabs.

  2. DoneJun 18, 2025

    Up to $40 billion committed

    TI put up to $40 billion toward the four Sherman fabs as part of more than $60 billion across Texas and Utah, and said SM2's shell was complete.

  3. DoneDec 17, 2025

    SM1 starts production

    TI began production at SM1, about three and a half years after breaking ground.

  4. NextNo date set

    SM2 fitted out and running

    SM2 will be equipped in line with market demand.

Worth knowing

Last checked Nov 21, 2026. We add a step when it happens and link the source.