Track your favorite projects · Chemicals
BASF Geismar MDI expansion
A $1 billion plant that nearly doubles BASF's output of MDI, a key ingredient in foam insulation and other polyurethanes.
Show on the map: BASF Geismar MDI
- InvestmentAbout $1 billion, BASF's largest wholly owned project in North AmericaBASF, Nov 11, 2026
- CapacityAbout 600,000 metric tons of MDI a year, almost doubleBASF, Nov 11, 2026
- New MDI plant$780 million of the total, 37 permanent jobsThe Advocate, Nov 12, 2026
- BuiltThree phases from 2018 to 2026BASF, Nov 11, 2026
Next gate
Full production rates
No date set
The plant started up a few months before the opening and is still ramping up. BASF says it has been tested at full rates but gave no date for running there.
Every step so far, and what comes next
-
Done2018
Expansion begins
BASF began a three phase plan to expand MDI output at Geismar.
Source: BASF, Nov 11, 2026
-
Done2020
New MDI synthesis unit
The first phase, a new MDI synthesis unit, went into service.
Source: BASF, Nov 11, 2026
-
Done2021
Upstream units expanded
The second phase expanded several upstream units.
Source: BASF, Nov 11, 2026
-
DoneFeb 27, 2026
Start up set for Q3 2026
BASF told investors the Geismar expansion was nearly complete, with start up planned in the third quarter of 2026.
Source: BASF, Feb 27, 2026
-
DoneNov 11, 2026
New plant opened
BASF opened the final phase, new upstream units and a splitter, and called it the largest MDI operation in North America.
Source: BASF, Nov 11, 2026 · On X: post
-
NextNo date set
Full production rates
The site manager said the plant is not yet at full capacity while it ramps up.
Source: The Advocate, Nov 12, 2026
Worth knowing
- The $1 billion covers all three phases since 2018, not just the new MDI unit.
- The new unit replaces an older MDI plant, so not all of the new capacity is added on top.
- The map pin is approximate, at the Geismar site in Ascension Parish.
Our posts on this build
Last checked Nov 21, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.