Track your favorite projects · Geothermal power
Fervo Cape Station
Oilfield drilling turned into round-the-clock power from deep hot rock.

Show on the map: Cape Station
- Planned sizeAbout 500 MW (100 MW Phase I, 400 MW Phase II)IEEE Spectrum (from Canary Media), Oct 12, 2026
- Running now33 MW first GeoBlock, in service Sep 30, 2026Fervo Energy, Oct 1, 2026
- Biggest buyerGoogle, 396 MW for 15 yearsFervo Energy, Nov 9, 2026
- Reserved transmission505 MW of long-term firm rights (400 MW existing plus a new 105 MW agreement)Fervo Energy, Nov 18, 2026
Next gate
GeoBlocks 2 and 3 enter commercial service
By Jan 1, 2027 (company target)
GeoBlock 2 is synced to the grid and sending test energy. GeoBlock 3 is mechanically complete and in cold commissioning. Together they would finish Phase I at about 100 MW.
Progress

Photo: Braddah n8 via Wikimedia Commons, CC0, Aug 31, 2025
Every step so far, and what comes next
-
DoneSep 30, 2026
First 33 MW GeoBlock enters commercial service
Fervo said the first unit reached commercial operation ahead of schedule.

Photo: Fervo Energy, Official press image, Oct 1, 2026 Source: Fervo Energy, Oct 1, 2026 · On X: post
-
DoneNov 9, 2026
GeoBlock 2 synced, Google deal signed
GeoBlock 2 achieved grid sync and is delivering test energy; GeoBlock 3 is mechanically complete. Fervo signed a 15-year, 396 MW take-or-pay deal with Google for GeoBlocks 4 through 11, and an independent study put the site's potential at about 8.4 GW.
Source: Fervo Energy, Nov 9, 2026
-
DoneNov 18, 2026
105 MW transmission agreement with Longroad Energy
Fervo signed a 105 MW long-term transmission service agreement with Longroad Energy, bringing Cape Station to 505 MW of reserved firm transmission on the Milford Gen Lead line. The new agreement is expected to begin in 2028, subject to final regulatory approvals.
Source: Fervo Energy, Nov 18, 2026 · On X: post
-
NextBy Jan 1, 2027company target
Phase I complete, about 100 MW
GeoBlocks 2 and 3 are expected to reach commercial operation, completing Phase I.
Source: Fervo Energy, Nov 9, 2026
-
ExpectedMid-2028company target
First power for Google
First power from GeoBlocks 4 through 11 under the Google agreement is expected in mid-2028.
Source: Fervo Energy, Nov 9, 2026
-
Expected2028company target
Phase II, another 400 MW
The remaining 400 MW is slated for 2028.
Worth knowing
- The 505 MW figure is reserved long-term firm transmission, not capacity already built. The new 105 MW agreement is expected to begin in 2028, subject to final regulatory approvals.
- Fervo has not published a total project cost. The $2 billion plus figure on our map comes from Canary Media and The Wall Street Journal.
- The 8.4 GW resource figure is an estimate of heat in place, not a construction plan.
Go deeper
Our posts on this build
- Post on: First 33 MW GeoBlock enters commercial service
- Post on: 105 MW transmission agreement with Longroad Energy
Last checked Nov 19, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.