Project Mica data center campus, Kansas City Northland
Google's second Kansas City campus: five hyperscale buildings on nearly 500 acres by the Nashua power station.
Show on the map: Project Mica
- FinancingUp to $10 billion in Port KC revenue bondsPort KC, 2025
- SizeFive buildings, 1.56 million square feet of IT spacePort KC, 2025
- PowerNearly 700 MW at full build outPort KC, 2025
- SiteNearly 500 acres at I-435 and Highway 169Port KC, 2025
Next gate
First building finished
About 18 months after the start (Port KC)
Port KC says the first phase, from site prep through the first data center building, is expected to take about 18 months. Construction was confirmed underway in February 2026.
Every step so far, and what comes next
-
DoneJul 2025
Port KC authorizes up to $10 billion in bonds
Port KC approved up to $10 billion in taxable revenue bonds plus a 25 year, 75% property tax break for the project.
Source: KSHB 41, Feb 12, 2026
-
DoneFeb 12, 2026
Google confirms it is building
Google said it is behind Project Mica and that construction is underway. Under its Evergy deal, Google says it will cover the full energy costs of both of its Kansas City campuses.
Source: KSHB 41, Feb 12, 2026
-
NextAbout 18 months incompany target
First phase done
The first phase ends with the first data center building.
Source: FOX4 Kansas City, Feb 13, 2026
Worth knowing
- The $10 billion is the most Port KC may issue in bonds, not a confirmed construction cost.
- Google confirmed its role and the construction through a statement to local news, not a formal announcement with a cost.
- Timing of later phases has not been published.
Last checked Nov 20, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.