Track your favorite projects · Iron ore and steel
Mesabi Metallics mine and Iowa steel mill
The first new US iron ore mine in 50 years, feeding a new steel mill downriver.
Show on the map: Nashwauk mine · Lee County mill
- Minnesota mineClose to $3 billion investedMesabi Metallics, Sep 29, 2026
- Iowa steel complex$15 billion, at least 1,750 jobsMesabi Metallics, Sep 29, 2026
- Construction jobsMore than 1,500 at the mine; 6,000+ planned in IowaMesabi Metallics, Sep 29, 2026
Next gate
First pellets at Nashwauk
"In coming weeks" (company statement)
Mesabi says it plans to begin producing direct-reduction iron ore pellets at Nashwauk soon. In Iowa, the company has filed a preliminary air permit and is still securing land near the Mississippi.
Every step so far, and what comes next
-
DoneSep 2026
$18 billion mine-to-mill plan announced
Mesabi announced a $15 billion steel complex in Iowa on top of the nearly $3 billion Minnesota mine, with more than 1,500 construction workers at the mine.
Source: Mesabi Metallics, Sep 29, 2026
-
DoneEarly Oct 2026
Iowa amends its MEGA incentive
Iowa's legislature amended the Major Economic Growth Attraction program, allowing up to about $1.4 billion in tax credits for the mill.
Source: Mesabi Tribune, Nov 14, 2026
-
DoneNov 11, 2026
Lee County votes yes
Supervisors unanimously approved the tax and community benefit term sheet and a resolution supporting the plant.
Source: KWQC, Nov 11, 2026 · On X: post, reply
-
NextComing weeks
First pellets at Nashwauk
Mesabi plans to begin producing direct-reduction pellets at Nashwauk.
Source: Mesabi Tribune, Nov 14, 2026
-
ExpectedBy end of 2027company target
Iowa groundbreaking
The target is to break ground on the Iowa mill by the end of 2027.
Source: KBUR, Nov 5, 2026
-
Expected2030company target
Iowa steel production
Steel production in Iowa would begin in 2030.
Source: Mesabi Tribune, Nov 14, 2026
Worth knowing
- Iowa dates are targets: groundbreaking by the end of 2027 and steel production in 2030, as reported by local outlets.
- Neighbors raised concerns about water use and construction traffic at the Nov 4 Lee County meeting.
Our posts on this build
Last checked Nov 19, 2026. We add a step when it happens and link the source.