Track your favorite projects · Fuels

Montana Renewables MaxSAF expansion, Great Falls

Calumet (Montana Renewables) · Great Falls, Montana

Expanding in steps, tie in turnaround next

A Great Falls refinery turning seed oils and tallow into jet fuel, now growing by reusing the asphalt plant next door.

Show on the map: Montana Renewables MaxSAF

Next gate

Tie in turnaround

Q4 2026

Montana Renewables plans a fourth quarter 2026 shutdown to tie a hydrotreater, hydrogen plant and naphtha splitter from the neighboring Calumet asphalt refinery into the renewable fuels plant. It expects to pass an 80 million gallon SAF run rate by the end of 2026.

Every step so far, and what comes next

  1. DoneJan 10, 2025

    $1.44 billion DOE loan closed

    Calumet closed a federal loan guarantee to expand the Great Falls plant, then aimed at about 300 million gallons of SAF a year.

  2. DoneSpring 2026

    Bottlenecks removed

    After work at the spring 2026 turnaround, the plant was producing at a 60 million gallon a year SAF run rate.

  3. DoneSep 1, 2026

    Cheaper expansion plan

    The company swapped the $1.2 billion megaproject for six small projects that reuse equipment from the neighboring asphalt refinery, at $137 million of remaining capital.

  4. DoneSep 14, 2026

    Final DOE draw received

    Montana Renewables received its last $34 million under the amended DOE loan.

  5. DoneNov 5, 2026

    Equipment lease signed

    Calumet Montana Refining signed a long term lease giving Montana Renewables the equipment for the expansion, for about $30 million a year.

  6. NextQ4 2026company target

    Tie in turnaround

    Turnaround to connect the leased equipment, with the SAF run rate expected above 80 million gallons by year end.

  7. ExpectedSpring 2027company target

    120 million gallon run rate

    The company expects to pass 120 million gallons a year by spring 2027.

  8. ExpectedEnd of 2028company target

    About 200 million gallons a year

    Target run rate for sustainable aviation fuel.

Worth knowing

Our posts on this build

Last checked Nov 20, 2026. We add a step when it happens and link the source.