Bagdad copper mine expansion
Doubling an 80-year-old copper mine with an autonomous truck fleet.

- InvestmentAbout $4.5 billionFreeport-McMoRan, Nov 4, 2026
- Copper outputOver 400 million lb a year (about 225 million more)Freeport-McMoRan, Nov 4, 2026
- Construction jobsMore than 4,000 direct and indirectFreeport-McMoRan, Nov 4, 2026
Next gate
Engineering, procurement and early works
Underway; about 20% of spending in 2027
Freeport is advancing engineering and early works. Construction is expected to take about 3.5 years.
Every step so far, and what comes next
-
Done2025
Fully autonomous haul fleet
Bagdad became the first major US mine with a fully autonomous haulage fleet.
Source: Freeport-McMoRan, Nov 4, 2026
-
DoneNov 4, 2026
Board approves $4.5 billion expansion
The plan more than doubles mining and milling rates with a new concentrator, crusher, conveyor, water pipeline and power line.
Source: Freeport-McMoRan, Nov 4, 2026 · On X: post
-
Next2027company target
Spending ramps up
About 20% of project costs are expected in 2027, 30 to 35% in 2028 and the rest in 2029 to 2030.
Source: Freeport-McMoRan, Nov 4, 2026
-
ExpectedMid-2030company target
Initial production from the expansion
Initial production is targeted for mid-2030, making Bagdad the second largest US copper mine.
Source: Freeport-McMoRan, Nov 4, 2026
Worth knowing
- Freeport notes that inflation and cost escalation could affect its estimates. The spending is classed as discretionary under its financial policy.