ACCESS Oklahoma turnpike long range plan
A 15-year, $8.2 billion plan to widen existing turnpikes, add interchanges and finish new routes around Oklahoma City.
Show on the map: ACCESS Oklahoma turnpike long range plan
- Investment$8.2 billion total program investment for 2022 to 2037, including inflation and contingency as of January 2026Oklahoma Turnpike Authority, Aug 25, 2026
- ScopeLane additions, new interchanges, bridge and pavement work, and new routes to complete the Oklahoma City Outer Loop and an I-35 relieverOklahoma Turnpike Authority, Aug 25, 2026
- FundingTurnpike revenue bonds, not state tax dollars. The Oklahoma Supreme Court affirmed the bond validation in August 2023Oklahoma Turnpike Authority, Aug 25, 2026
- ProgressAs of June 4, 2026, OTA had invoiced more than $740 million, let 20 construction projects, and authorized a third bond issue of up to $1.5 billion. More than 20 additional projects, valued at more than $700 million, were scheduled for potential award through the end of 2026Oklahoma Turnpike Authority, Jun 4, 2026
Next gate
Haikey Creek traffic switch
Expected in late fall 2026
The June 2026 board update said traffic on the Creek Turnpike was expected to switch to the new eastbound Haikey Creek bridge in late fall 2026 so work could begin on the westbound bridge.
Every step so far, and what comes next
-
DoneAugust 2023
Bond validation upheld
The Oklahoma Supreme Court affirmed OTA's bond validation, allowing ACCESS Oklahoma projects to move forward.
-
DoneJune 4, 2026
Third bond issue authorized
The OTA Board authorized up to $1.5 billion in revenue bonds, the program's third issuance, and reported more than $740 million already invoiced.
-
NextLate fall 2026
Haikey Creek traffic switch
Traffic was expected to switch to the new eastbound Haikey Creek bridge so work could begin on the westbound span.
Worth knowing
- ACCESS Oklahoma is a multi-corridor program. The map pin is approximate, on the Turner Turnpike east of Oklahoma City.
- The $8.2 billion figure is OTA's published total as of January 2026, in the 2026 Outlook. Later news reports have said the estimate may rise toward $9 billion with added Turner Turnpike scope. This page keeps the official published figure used on the map.
- The late-fall 2026 Haikey Creek date was given in June 2026 and may move.
Last checked Nov 23, 2026. We add a step when it happens and link the source.