AESC battery plant, Bowling Green
A $2 billion, 30 gigawatt-hour battery plant that officially broke ground on August 30, 2022. Later official 2023 materials targeted an early 2025 opening, and this pass did not find a later official confirmation that production had begun.
Show on the map: AESC battery plant, Bowling Green
- InvestmentThe Kentucky Cabinet for Economic Development announced on April 13, 2022, that Envision AESC would invest $2 billion, the figure used on the map, to build a 30 gigawatt-hour gigafactory at the Kentucky Transpark in Bowling Green, creating 2,000 jobsKentucky Cabinet for Economic Development, Apr 13, 2022
- GroundbreakingOn August 30, 2022, Governor Andy Beshear joined Envision AESC to break ground on the $2 billion plant. That official release described an approximately 3 million square foot operation and said the plant had the potential to expand to 40 gigawatt-hoursKentucky Cabinet for Economic Development, Aug 30, 2022
- Structural steel and later official statusOn September 14, 2023, the Cabinet announced that Governor Beshear had joined AESC leaders to place the last piece of structural steel at a 1.6 million square-foot, $2 billion gigafactory, and that the factory was on track for an early 2025 opening. This pass did not find a later official company or state announcement confirming that production had started, or a later official change in construction status, so the tracker stage remains under construction, matching the mapKentucky Cabinet for Economic Development, Sep 14, 2023
Next gate
No later official confirmation of opening found this pass
Early 2025 opening was the target in the September 14, 2023 official announcement; later official confirmation not found
The official September 14, 2023 announcement said the factory was on track for an early 2025 opening. This pass did not find a later official confirmation that the plant had opened or begun production, so that milestone is not marked complete.
Every step so far, and what comes next
-
DoneApril 13, 2022
Kentucky announced the $2 billion gigafactory
Governor Beshear and Envision AESC announced a 30 gigawatt-hour plant at the Kentucky Transpark, expected to create 2,000 jobs.
Source: Kentucky Cabinet for Economic Development, Apr 13, 2022
-
DoneAugust 30, 2022
Official groundbreaking
Governor Beshear joined Envision AESC to break ground on the $2 billion plant.
Source: Kentucky Cabinet for Economic Development, Aug 30, 2022
-
DoneSeptember 14, 2023
Last structural steel placed
The official state release said the last piece of structural steel was placed and that the factory was then on track for an early 2025 opening.
Source: Kentucky Cabinet for Economic Development, Sep 14, 2023
-
NextEarly 2025, as targeted in 2023; later official confirmation not found
Opening targeted in 2023 materials; later official confirmation not found
The September 14, 2023 official announcement targeted an early 2025 opening. This pass did not find a later official confirmation that production had begun.
Source: Kentucky Cabinet for Economic Development, Sep 14, 2023
Worth knowing
- The official 2022 announcement described a plant of about 3 million square feet. The official September 14, 2023 topping-out announcement described a 1.6 million square-foot facility. Both official figures are recorded rather than collapsed into one number.
- The September 14, 2023 expectation of an early 2025 opening is not treated as a confirmed later milestone without a subsequent official confirmation.
- This page uses official state and company announcements only and does not rely on later secondary reporting about construction interruptions.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.