AIB data center upgrade, Tyger River Industrial Park

AIB CLT1 LLC · 389 Tyger River Industrial Drive, Moore, Spartanburg County, South Carolina

Permitted

Spartanburg County enacted Ordinance O-26-34 on November 16, 2026, authorizing a development agreement for a 50 IT megawatt data center at 389 Tyger River Industrial Drive, with an anticipated investment of $1.2 billion.

Show on the map: AIB data center upgrade, Tyger River Industrial Park

Next gate

Construction start after development approvals, as stated in the official agreement

No later than the first anniversary of the last development approval, or after any legal challenges have been resolved

The official development agreement says construction shall commence no later than the first anniversary of the last development approval, or after any legal challenges to those approvals have been resolved, and that substantial completion shall be achieved no later than the fifth anniversary of the issuance of the last development approval. This pass did not find a later official confirmation that construction had started. The map pin remains listed as permitted.

Every step so far, and what comes next

  1. DoneOctober 19, 2026

    First reading of the AIB development agreement ordinance

    The official clerk's certificate attached to Ordinance O-26-34 states that the ordinance was given readings at the County Council meetings of October 19, 2026, November 3, 2026, and November 16, 2026.

  2. DoneNovember 3, 2026

    Second reading of the AIB development agreement ordinance

    The official clerk's certificate states that the ordinance received a reading at the November 3, 2026 County Council meeting.

  3. DoneNovember 16, 2026

    County Council enacts Ordinance O-26-34

    Spartanburg County Council enacted Ordinance O-26-34 on November 16, 2026, authorizing the development agreement for a 50 IT megawatt data center at 389 Tyger River Industrial Drive, with an anticipated investment of $1.2 billion.

  4. NextNo later than the first anniversary of the last development approval, or after any legal challenges have been resolved

    Construction start after development approvals, as stated in the official agreement

    The official development agreement says construction shall commence no later than the first anniversary of the last development approval, or after any legal challenges to those approvals have been resolved, and that substantial completion shall be achieved no later than the fifth anniversary of the issuance of the last development approval. This pass did not find a later official confirmation that construction had started. The map pin remains listed as permitted.

Worth knowing

Go deeper

Last checked Nov 24, 2026. We add a step when it happens and link the source.