Aluminum Dynamics mill, Columbus

Steel Dynamics · Columbus, Lowndes County, Mississippi

Commissioning

A $2.5 billion recycled aluminum flat-rolled mill that shipped its first coils in June 2025 and, as of Steel Dynamics' October 19, 2026 results, was still being commissioned and ramped.

Show on the map: Aluminum Dynamics mill, Columbus

Next gate

Second continuous annealing line targeted to become operational

Early in the first quarter of 2027

Steel Dynamics' October 19, 2026 official results said the second continuous annealing and solution heat line would be commissioned in the coming months and become operational early in the first quarter of 2027, while commissioning and customer qualification of the mill continued.

Every step so far, and what comes next

  1. DoneJune 2025

    First coils shipped

    Steel Dynamics' January 26, 2026 presentation said the mill shipped its first coils in June 2025.

  2. DoneOctober 19, 2026

    Third-quarter results described continued commissioning

    The company said all three cold mills were operational and that the first continuous annealing line was operating, while commissioning and ramp-up continued.

  3. NextEarly in the first quarter of 2027

    Second continuous annealing line targeted to become operational

    Official third-quarter 2026 results said the second line would be commissioned in the coming months and become operational early in the first quarter of 2027.