Aluminum Dynamics mill, Columbus
A $2.5 billion recycled aluminum flat-rolled mill that shipped its first coils in June 2025 and, as of Steel Dynamics' October 19, 2026 results, was still being commissioned and ramped.
Show on the map: Aluminum Dynamics mill, Columbus
- InvestmentSteel Dynamics' January 26, 2026 investor presentation listed a $2.5 billion investment for the recycled aluminum flat-rolled mill, the figure used on the map, and a separate approximately $400 million investment for two satellite recycled aluminum slab centers, which are not pinned here. The mill is designed for 650,000 tonnesSteel Dynamics, Jan 26, 2026
- First coilsThe same official presentation said the mill shipped its first coils in June 2025 and had produced industrial, beverage-can, and automotive-quality flat-rolled aluminum productsSteel Dynamics, Jan 26, 2026
- Commissioning status, as of October 2026Steel Dynamics' official aluminum page says the company is currently commissioning the aluminum flat-rolled products mill. In its October 19, 2026 third-quarter results, the company said the team continues to commission, qualify, and ramp up the mill, that all three cold mills were then operational, that the first of two continuous annealing and solution heat lines was operating, and that the second such line would be commissioned in the coming months and become operational early in the first quarter of 2027Steel Dynamics, Oct 19, 2026
Next gate
Second continuous annealing line targeted to become operational
Early in the first quarter of 2027
Steel Dynamics' October 19, 2026 official results said the second continuous annealing and solution heat line would be commissioned in the coming months and become operational early in the first quarter of 2027, while commissioning and customer qualification of the mill continued.
Every step so far, and what comes next
-
DoneJune 2025
First coils shipped
Steel Dynamics' January 26, 2026 presentation said the mill shipped its first coils in June 2025.
Source: Steel Dynamics, Jan 26, 2026
-
DoneOctober 19, 2026
Third-quarter results described continued commissioning
The company said all three cold mills were operational and that the first continuous annealing line was operating, while commissioning and ramp-up continued.
Source: Steel Dynamics, Oct 19, 2026
-
NextEarly in the first quarter of 2027
Second continuous annealing line targeted to become operational
Official third-quarter 2026 results said the second line would be commissioned in the coming months and become operational early in the first quarter of 2027.
Source: Steel Dynamics, Oct 19, 2026
Worth knowing
- The map figure is the official $2.5 billion rolling-mill investment in the January 26, 2026 presentation. The approximately $400 million for two satellite slab centers is a separate official figure and is not added to the pin.
- First-coil shipments in June 2025 are not treated as the end of commissioning. Official October 2026 materials still describe commissioning and ramp-up as underway.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.