Amkor advanced packaging campus, Peoria
A multi-phase outsourced packaging and test campus in Peoria. The first plant is due in mid-2027, with production in early 2028.
Show on the map: Amkor advanced packaging campus
- Investment on the map$7 billion across two phases, announced at the Oct 6, 2025 groundbreaking when Amkor raised the plan by more than $5 billionArizona Commerce Authority, Oct 6, 2025
- Later planned totalAbout $12 billion, after a Sept 8, 2026 Phase 2 announcement that added about 60,000 square meters of cleanroom spaceAmkor Technology, Sep 8, 2026
- Phase 1 timingConstruction of the first manufacturing facility is expected to be completed in mid-2027, with production beginning in early 2028Arizona Commerce Authority, Oct 6, 2025
- JobsUp to 3,000 jobs in the 2025 two-phase plan. The 2026 Phase 2 announcement said both phases are expected to support more than 3,500 Arizona-based employeesArizona Commerce Authority, Oct 6, 2025
Next gate
First facility construction complete
Mid-2027 (company target)
Amkor's October 2025 groundbreaking said construction of the first manufacturing facility was expected to be completed in mid-2027, with production in early 2028.
Every step so far, and what comes next
-
DoneOct 6, 2025
Groundbreaking and $7 billion plan
Amkor broke ground in Peoria and raised the planned investment to $7 billion across two phases, with more than 750,000 square feet of cleanroom space.
-
DoneSept 8, 2026
Phase 2 expanded to about $12 billion
Amkor announced a larger Phase 2, raising the planned campus investment to about $12 billion, with Phase 2 construction anticipated in late 2027 and completion by the end of 2029.
Source: Amkor Technology, Sep 8, 2026
-
NextMid-2027
First facility construction complete
The October 2025 target for finishing the first manufacturing facility.
-
ExpectedLate 2027
Phase 2 construction starts
Amkor's September 2026 announcement said Phase 2 construction is anticipated to begin in late 2027.
Source: Amkor Technology, Sep 8, 2026
-
ExpectedEarly 2028
First production
The October 2025 target for the start of production.
-
ExpectedEnd of 2029
Phase 2 complete
The September 2026 target for finishing Phase 2.
Source: Amkor Technology, Sep 8, 2026
Worth knowing
- The map counts $7 billion, the October 2025 two-phase figure. Amkor later said the planned investment rose to about $12 billion. The map figure has not been changed here.
- The 2025 jobs figure was as many as 3,000. The later Phase 2 plan is more than 3,500 for both phases.
- Dates are company targets.
Last checked Nov 23, 2026. We add a step when it happens and link the source.