Applied Digital Polaris Forge 2, Harwood
A $3 billion AI factory campus that Applied Digital officially said had broken ground after August 31, 2025, with an initial 200 megawatts expected to begin coming online in 2026.
Show on the map: Applied Digital Polaris Forge 2, Harwood
- Investment$3 billion, the figure used on the map, from Applied Digital's August 18, 2025 announcement of the Polaris Forge 2 campus near Harwood. That release described a 280 megawatt AI factory designed to scale beyond the initial capacity, with more than 900 acres contracted and power to be secured through Cass County Electric CooperativeApplied Digital, Aug 18, 2025
- Groundbreaking and constructionApplied Digital's October 9, 2025 fiscal first quarter 2026 results said that, subsequent to the quarter ended August 31, 2025, the company broke ground on Polaris Forge 2. The October 22, 2025 lease announcement described the campus as currently under constructionApplied Digital, Oct 9, 2025
- Lease and later official capacityOn October 22, 2025, Applied Digital announced an approximately 15-year lease with a U.S. based investment-grade hyperscaler for 200 megawatts of critical IT load at Polaris Forge 2, with about $5 billion in contracted revenue over the term. That release said the initial 200 megawatts are phased within two buildings expected to begin to come online in 2026 and reach a total of 200 megawatts in 2027, and it described the full expansion potential of the campus as 1 gigawatt, including a first right of refusal for an additional 800 megawattsApplied Digital, Oct 22, 2025
- Construction financingOn March 4, 2026, Applied Digital announced the pricing of a $2.15 billion offering of senior secured notes due 2031, with net proceeds intended to fund development and construction of 200 megawatts of critical IT load at Polaris Forge 2. That note issue is financing for the initial 200 megawatts, not a replacement for the map's $3 billion campus figureApplied Digital, Mar 4, 2026
- Jobs, from the original announcementThe August 18, 2025 announcement said that once fully operational, the site was expected to employ more than 200 full-time employees, in addition to long-term contractorsApplied Digital, Aug 18, 2025
Next gate
Initial 200 megawatts begin to come online
2026
The October 22, 2025 official lease announcement said the initial 200 megawatts, in two buildings, are expected to begin to come online in 2026 and reach a total of 200 megawatts in 2027.
Every step so far, and what comes next
-
DoneAugust 18, 2025
Campus announced at $3 billion
Applied Digital announced plans to break ground in September 2025 on the $3 billion Polaris Forge 2 campus near Harwood.
Source: Applied Digital, Aug 18, 2025
-
DoneSubsequent to August 31, 2025, reported October 9, 2025
Official groundbreaking
In its fiscal first quarter 2026 results, Applied Digital said that subsequent to the quarter ended August 31, 2025, it broke ground on Polaris Forge 2.
Source: Applied Digital, Oct 9, 2025
-
DoneOctober 22, 2025
200 megawatt hyperscaler lease announced
Applied Digital announced an approximately 15-year, 200 megawatt lease at the under-construction campus, with initial delivery beginning in 2026.
Source: Applied Digital, Oct 22, 2025
-
Next2026
Initial 200 megawatts begin to come online
The October 22, 2025 lease announcement said the initial 200 megawatts are expected to begin to come online in 2026 and reach a total of 200 megawatts in 2027.
Source: Applied Digital, Oct 22, 2025
Worth knowing
- Official capacity descriptions changed after the August 18, 2025 announcement. That release described a $3 billion, 280 megawatt campus with initial operations in 2026 and full capacity in early 2027. The October 9, 2025 earnings release referred to an approximately $3 billion, 300 megawatt IT load campus, with the initial 200 megawatts expected to begin to come online in 2026 and reach full capacity in 2027. The October 22, 2025 lease release then described 200 megawatts under lease and a 1 gigawatt expansion potential. This page keeps the map's $3 billion figure and records those later official capacity figures without replacing the map total.
- The approximately $5 billion figure in the October 22, 2025 release is contracted lease revenue, not the campus construction budget.
- The $2.15 billion note offering announced March 4, 2026 is construction financing for 200 megawatts, not a new official project budget.
- A secondary news date of September 15, 2025 for the start of construction was not used. The official grounding is Applied Digital's October 9, 2025 statement that groundbreaking occurred subsequent to the quarter ended August 31, 2025.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.