AVAIO Digital Leo campus, Little Rock
A multi-phase AI-ready data center and power campus, with a first-phase investment of $6 billion.
Show on the map: AVAIO Digital Leo campus, Little Rock
- Investment$6 billion for the first phase, a combined investment from AVAIO and its customers in infrastructure, power, and tenant deployments. AVAIO's CEO also described more than $21 billion through full development; the map counts the $6 billion first-phase figureArkansas Economic Development Commission, Jan 12, 2026
- Power, 2026 announcementAVAIO said it was contracted with Entergy Arkansas for 150 megawatts, with anticipated demand of up to 1 gigawatt as the campus grows. The announcement said the contracted 150 megawatts would be energized in the second quarter of 2027Arkansas Economic Development Commission, Jan 12, 2026
- Power, company campus pageAVAIO's campus page lists 1,070 megawatts of total baseload power (570 megawatts of grid power and 500 megawatts of behind-the-meter baseload) and an executed Entergy Arkansas agreement for initial grid capacity energized in the fourth quarter of 2027AVAIO Digital, Nov 23, 2026
- JobsMore than 500 full-time permanent operations jobs over the next five years as the campus is built out, plus thousands of construction jobs, according to the January 2026 announcementArkansas Economic Development Commission, Jan 12, 2026
- ProgressAVAIO's campus page, checked on Nov 23, 2026, says the company has broken ground on Project Leo, a 296-acre project with initial fully contracted capacity online by 2027AVAIO Digital, Nov 23, 2026
Next gate
Initial capacity online and energized
2027, with official dates that do not all match
The January 12, 2026 announcement said first-phase construction would be complete and energized in June 2027, and that 150 megawatts of grid power would be energized in the second quarter of 2027. AVAIO's current campus page says initial fully contracted capacity is online by 2027 and that initial Entergy grid capacity is to be energized in the fourth quarter of 2027.
Every step so far, and what comes next
-
DoneJanuary 12, 2026
Leo campus announced
AVAIO Digital announced a $6 billion first-phase data center and power campus near Little Rock, with first-phase construction then expected to start in the first quarter of 2026.
Source: Arkansas Economic Development Commission, Jan 12, 2026
-
DoneBy late 2026
Groundbreaking stated on the company campus page
AVAIO's campus page says the company has broken ground on Project Leo. The page does not give a dated ceremony.
Source: AVAIO Digital, Nov 23, 2026
-
Next2027
Initial capacity online and energized
Dates in the announcement and on the current campus page point to 2027 but do not all match; see caveats.
Source: Arkansas Economic Development Commission, Jan 12, 2026
Worth knowing
- The map counts the $6 billion first-phase figure. The January 2026 announcement also quoted a full-development figure of more than $21 billion. This page does not change the map dollars.
- Official acreage figures differ. The January 2026 announcement described a 760-acre site. AVAIO's campus page now describes a 296-acre project. This page records both.
- Official energization timing also differs: June 2027 or the second quarter of 2027 in the announcement, and the fourth quarter of 2027 on the current campus page.
- The campus page says the company has broken ground but does not give a ceremony date. The map pin is approximate.
Last checked Nov 23, 2026. We add a step when it happens and link the source.