WBI Energy Bakken East natural gas pipeline
An approximately 350 mile natural gas pipeline with a positive final investment decision on September 30, 2026, estimated at $2.7 to $3.2 billion, with construction planned for 2028 to 2030.
Show on the map: WBI Energy Bakken East natural gas pipeline
- InvestmentMDU Resources announced a positive final investment decision on September 30, 2026, and estimated the project would cost between $2.7 and $3.2 billion. The map counts the $2.7 billion low end of that official rangeMDU Resources Group, Sep 30, 2026
- ScopeThe approximately 350 mile pipeline will run from the Bakken region in western North Dakota to a location near Fargo in eastern North Dakota, with an initial design capacity of 1.4 billion cubic feet per day. When completed, the project will include additions and modifications at three existing WBI Energy compressor stations and the construction of four new compressor stations. The second phase ends at an existing WBI Energy compressor station near MapletonMDU Resources Group, Sep 30, 2026
- ScheduleConstruction is expected to occur over construction seasons in 2028 through 2030, with facilities placed in service in two phases. The first phase, from the Bakken to central North Dakota, is expected to be complete in late 2029. The second phase, to the Mapleton compressor station, has a target completion date of late 2030. Because construction is planned to start in 2028, the tracker stage remains announced, matching the mapMDU Resources Group, Sep 30, 2026
- State capacity commitmentThe company said the North Dakota Industrial Commission voted unanimously in August 2025 to support the project with a firm capacity commitment of $50 million per year for 10 years. That is a capacity payment commitment, not an addition to the construction cost rangeMDU Resources Group, Sep 30, 2026
Next gate
Construction planned to begin
2028
The September 30, 2026 official announcement said construction is expected in 2028 through 2030, with the first phase complete in late 2029 and the second phase targeted for late 2030.
Every step so far, and what comes next
-
DoneAugust 2025
North Dakota Industrial Commission backed firm capacity
MDU said the commission voted unanimously in August 2025 to support the project with a firm capacity commitment of $50 million per year for 10 years.
-
DoneSeptember 30, 2026
Positive final investment decision
The MDU Resources board reached a positive final investment decision for WBI Energy to construct the Bakken East Pipeline.
-
Next2028
Construction planned to begin
The official announcement said construction is expected over the 2028 through 2030 seasons, with first-phase service in late 2029 and second-phase service targeted for late 2030.
Worth knowing
- The official cost is a range of $2.7 to $3.2 billion. The map uses the $2.7 billion low end and does not treat the top of the range as the project total.
- The final investment decision is not a construction start. Official materials plan construction for 2028 through 2030, so the stage remains announced.
- The map pin is approximate, at the Mapleton end of the line in Cass County. The pipeline is planned to cross much of the state.
- The North Dakota Industrial Commission's $50 million per year capacity commitment is not added to the capital range.
Last checked Nov 23, 2026. We add a step when it happens and link the source.